Mumbai/Project record

MahaRERA · the public record

KHUSHI AANGAN PHASE II

Manor · KHUSHI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000004653

Delivery and registration

When is the project declared for completion?

KHUSHI AANGAN PHASE II is registered with MahaRERA as P99000004653 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000004653
Registered on09 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KHUSHI AANGAN PHASE II record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Khushi Developers is the promoter of record on 22 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

22projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KHUSHI AANGAN PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
111G+430 Jun 2021
121G+430 Jun 2021
131G+430 Jun 2021
141G+430 Jun 2021
151G+430 Jun 2021
161G+430 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Change of Partners with Retirement of Three Partners and Admission of New Partner. Due to Pandemic and Covid19 1st wave and 2nd wave Situation.

Location, Land & Connectivity

Located at Manor, Manor, Borivali, Mumbai Suburban, 401404. Per the filed land record, the plot is bounded to the north by ROAD, to the south by LAND GUT NO 212, to the east by LAND GUT NO 213 and to the west by LAND GUT NO 258. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~66 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ66 km
Powai / Hiranandani business park68 km
Chhatrapati Shivaji Int'l Airport71 km
Bandra Kurla Complex (BKC)74 km
Lower Parel / Worli business district81 km
Nariman Point / Fort90 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Khushi Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Khushi Developers

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Kiara
possession by Jun 2029 · Niwas Lifespaces LLP
Kingsmarque Heights
possession by Aug 2027 · Kingsmarque Developers
Kini Pinnacle
possession by Dec 2028 · Kini Lifespace Developers
Kinjal Bliss
possession by Dec 2028 · Kinjal Homes
Kinjal Complex
declared completion Jun 2018 · Kinjal Enterprises
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026