MahaRERA Property Intelligence · Raigarh

Konnark River City

P52000010087 · Panvel · promoter Konnark Township Pvt

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52000010087
Registered on23 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Konnark Township Pvt is the promoter of record on 111 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
121G+25-
131G+14-
141G+14-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000001228306/12/2017ganesh bhagwan bhosale vs Konnark Township Pvt Ltdorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Senior Division PanvelSpl-CS No-237/20112011Next Date Hearing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202231 Dec 20211. The Promoter has till date neither advertised the said project nor booked, sold any units in the said project to any Purchasers. 2. The Promoter desires to extend the time for

Location, Land & Connectivity

Located at Panvel, Koproli, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by Survey no-27 hissa no-2, to the south by Survey no-23, to the east by Survey no-27 hissa no-3 and to the west by survey no-16 hissa no-3 and 4. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~29 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park29 km
Bandra Kurla Complex (BKC)31 km
Chhatrapati Shivaji Int'l Airport32 km
Andheri MIDC / SEEPZ33 km
Lower Parel / Worli business district34 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Konnark Stellar
possession by Dec 2032 · Konnark Stays
Koteshwari Heritage
declared completion Dec 2018 · Pddevelopers
Koyna Villa
declared completion Jun 2026 · Badar Group Builder And Developer
KPS Park
possession by Dec 2027 · KPS Enterprises
Krantibhumi Cooperative Housing Society -Silver Height
possession by Dec 2031 · Chandrakaumudi Construction
Kreston Tower
possession by Dec 2028 · Heritage Constech LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026