Mumbai/Project record

MahaRERA · the public record

Krishna

Vile Parle (west) ·

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

1units filed as unsoldInventory · 18 September 2026
31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
10registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800034652

Delivery and registration

When is the project declared for completion?

Krishna is registered with MahaRERA as P51800034652 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800034652
Registered on20 Apr 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Krishna record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Krishna, ₹15.75 Cr of a declared ₹15.75 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.

100.0%

₹15.75 Cr

of ₹15.75 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Krishna, 2 of 3 homes filed with MahaRERA are recorded as sold or booked, about 67%, and 1 remain available.

67%sold

2 of 3 homes

₹20.22 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹19.27 Cr (about 95%) is recorded as collected and ₹95.45 Lakh as receivable. The project registers 10 homes in total, while this sold/unsold inventory filing covers 3 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 55012,390 sqft (222.03 sqm)₹7.18 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Krishna in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 September 2026

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 2 homes carry one, and 1 of the 3 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 10 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Krishna1G+121031 Dec 2025

Unit mix on the filing: 10 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vile Parle (west), N S Road 3, JVPD Scheme, Mumbai City, Mumbai City, 400056. Per the filed land record, the plot is bounded to the north by Chirag Apartment, to the south by Bhavbindu Apartment, to the east by 40 feet road and to the west by Vrindavann Apartment. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other flagged projects by Not Available

Not Available
FlaggedMumbai Suburban

Other RERA-registered projects in Vile Parle West

Tulsidham CHS
possession by Sep 2026 · SM & Happy Home Associates
56 Park Avenue
possession by Dec 2026 · Krishang Infra Private Limited
Ajmera Shringaar
possession by Dec 2026 · H J Corporation
Durga Gayatri
possession by Dec 2026 · Manoj Mohanlal Goradia
Eden 62
possession by Dec 2026 · Ekta Nagpal Ventures LLP
Meera Kunj
possession by Dec 2026 · Arham Realty

Other RERA-registered projects in Mumbai Suburban

Krishna Bhavan SRA Housing Co.op.hsg.sty.ltd
declared completion Dec 2019 · Ganesh Star Builders
Krishna Coniq
possession by Dec 2030 · Skydome Realtors LLP
Krishna Curve
declared completion Dec 2023 · Krishna Minerals
Krishna Heights
possession by Dec 2028 · Sarvshubh Enterprises
Krishna Heritage
declared completion Dec 2022 · Krishna Enterprises
Krishna Kripa
declared completion Aug 2026 · Skyla Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026