Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP51800010330
Registered on24 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
B WING1G+7-
A WING1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil7548/20042004Record For Evidence

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by CHETNA APARTMENT, to the south by NELIMA APARTMENT, to the east by RECREATIONAL GROUND and to the west by NELIMA APRTMENT . Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Shraddha Evoque
possession by Aug 2026 · Shraddha Landmark Private Limited
Primo
possession by Sep 2026 · Ceear Land Developers LLP
Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Krishna Bhuvan
possession by Jun 2027 · Ashraj Developers Private Limited
Krishna Chaitanya Rajbhavan Chsl
declared completion Oct 2020 · Ethics Infra Development Pvt. Ltd.
Krishna Coniq
possession by Dec 2030 · Skydome Realtors LLP
Krishna Cooperative Housing Society Limited
declared completion Dec 2021 · Zenal Construction Private LTD
Krishna Enclave
declared completion Aug 2023 · Asha Developers
Krishna Heights
declared completion Dec 2025 · Radhe Krishna Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.