KRISHNA DHAM

Mumbai Suburban · KARMA CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700003812

Delivery and registration

When is the project declared for completion?

KRISHNA DHAM is registered with MahaRERA as P51700003812 and the promoter has declared completion for 31 Jul 2019.

31 Jul 2019

declared completion

86months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700003812
Registered on06 Aug 2017
Promoter-declared completion31 Jul 2019
Current statusCertificate Signed
Against todayabout 86 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KRISHNA DHAM record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Karma Construction is the promoter of record on 40 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

40projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KRISHNA DHAM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
KRISHNA DHAM BULD 21G+3-
KRISHNA DHAM BULD 11G+8-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for KRISHNA DHAM, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019748804/07/2021MEENA RAKESH SINGH vs KARMA CONSTRUCTIONorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2019Super structure already completed. Finishing work is in progress. Flooring is done till 4th floor. Infrastructure work is in progress, Already applied for permanent electric meter

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401105. Per the filed land record, the plot is bounded to the north by EXISTING BUILDING, to the south by EXISTING ROAD, to the east by EXISTING ROAD and to the west by EXISTING BUILDING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander East

Gayatri Elegance
possession by Dec 2026 · Gayatrikripa Developers Private Limited
Basera Heights
possession by Dec 2026 · Kamruddin Hasmullah Siddique
Durga Enclave
possession by Dec 2026 · Anmol Developers
Ranuja Ramdev C Type
possession by Dec 2026 · Ranuja Ramdev C Type
Surya Heritage A
possession by Dec 2026 · Arun Construction CO
The Pentagon
possession by Dec 2026 · Anjani Kumar Realty Private Limited

Other RERA-registered projects in Thane

Krishna Dham
declared completion Dec 2025 · Atree Realtors
Krishna Dham
declared completion Dec 2025 · Royal Group
Krishna Dham - 2
possession by Dec 2026 · Atree Realtors
Krishna Empire
declared completion Dec 2021 · Shree Balaji Homes
Krishna Empire
possession by Dec 2026 · Shree SAI Balaji Associates
Krishna Empire
declared completion Mar 2024 · K M Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026