MahaRERA Property Intelligence · Thane

KRISHNA DHAM

P51700003812 · promoter Karma Construction

Certificate SignedDue 31 Jul 2019

Delivery & Registration

MahaRERA registrationP51700003812
Registered on06 Aug 2017
Promoter-declared completion31 Jul 2019
Current statusCertificate Signed
Against todayabout 84 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Karma Construction is the promoter of record on 38 projects, of which 7 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
KRISHNA DHAM BULD 21G+3-
KRISHNA DHAM BULD 11G+8-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019748804/07/2021MEENA RAKESH SINGH vs KARMA CONSTRUCTIONorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jul 201931 Jul 2019Super structure already completed. Finishing work is in progress. Flooring is done till 4th floor. Infrastructure work is in progress, Already applied for permanent electric meter

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401105. Per the filed land record, the plot is bounded to the north by EXISTING BUILDING, to the south by EXISTING ROAD, to the east by EXISTING ROAD and to the west by EXISTING BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander East

Gayatri Elegance
possession by Dec 2026 · Gayatrikripa Developers Private Limited
Basera Heights
possession by Dec 2026 · Kamruddin Hasmullah Siddique
Durga Enclave
possession by Dec 2026 · Anmol Developers
Ranuja Ramdev C Type
possession by Dec 2026 · Ranuja Ramdev C Type
Surya Heritage A
possession by Dec 2026 · Arun Construction CO
The Pentagon
possession by Dec 2026 · Anjani Kumar Realty Private Limited

Other RERA-registered projects in Thane

Krishna Dham
declared completion Dec 2025 · Atree Realtors
Krishna Dham
declared completion Dec 2025 · Royal Group
Krishna Dham - 2
possession by Dec 2026 · Atree Realtors
Krishna Empire
declared completion Dec 2021 · Shree Balaji Homes
Krishna Empire
declared completion Feb 2021 · L K Earth Developers Private Limited
Krishna Empire
possession by Dec 2026 · Shree SAI Balaji Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026