KRISHNA PALACE

BORIVALI WEST · PANTAGON BUILT

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002538

Delivery and registration

When is the project declared for completion?

KRISHNA PALACE is registered with MahaRERA as P51800002538 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002538
Registered on01 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KRISHNA PALACE record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KRISHNA PALACE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
KRISHNA PALACE1G+2330 Dec 2023

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for KRISHNA PALACE, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004447611/05/2018JAGRUTI LAD vs Pantagon Builtorder passed
CC00600000019601115/02/2021Manjula Nandagopal vs Lucina Land Development Limitedorder passed
CC00600000019613623/02/2021MR. KRISHNARAJ M. POONJA AND MRS. RESHMA K. POONJA vs M/S PENTAGON BUILTorder passed
CC00600000019621902/03/2021MR. KRISHNARAJ MANJANNA POONJA AND MRS. RESHMA KRISHNARAJ POONJA vs M/S PENTAGON BUILT, MR. MUKESH RATILAL MAKWANA, MR. BHAVESH NAVNITLAL SHAHorder passed
CC00600000019743128/06/2021PANTAGON BUILT vs KRISHNARAJ MANJANNA POONJAorder passed
CC00600000019599812/02/2021Colin Desa vs M/s Pantagon Builtorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023The primary reasons of delay was obtaining approvals on time for the Rehab building and Sale Building. Enormous numbers of compliance, lengthy procedures for required permissions,
30 Dec 202330 Dec 2025Further Permissions as well as Rehab Tenant flat handover balance and Occupation Certificate Balance.

Location, Land & Connectivity

Located at BORIVALI WEST, EKSAR ROAD, Borivali, Mumbai Suburban, 400091. Per the filed land record, the plot is bounded to the north by CTS - 314 PART, to the south by NALLA, to the east by EKSAR ROAD and to the west by NALLA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Bhoomi Pratishtha
possession by Oct 2026 · Bhoomi Shashwat Estate Pvt. Ltd.
Bank OF India Employees Sukhada Chsl
possession by Dec 2026 · M/S Hirani Realtors
Jaykant Bliss
possession by Dec 2026 · Chitalia Builders
Gagansagar
possession by Dec 2026 · HUM Developers Private Limited
Empire Meghna
possession by Mar 2027 · Empire Realty
Goyal Nrupa Square
possession by Mar 2027 · Parshwa Amrit

Other RERA-registered projects in Mumbai Suburban

Krishna Residency
possession by Dec 2027 · Rangoli Developers
Krishnagiri Upavan CO-Operative Housing Society Limited
possession by Dec 2029 · Samarpan Homes & Developers
Krishnaraj Buildcon NEW Suryadarshan CO OP Hsg. SOC
possession by Dec 2027 · Krishnaraj Buildcon
Krishvi Residency
possession by Dec 2027 · Shagun Chembur
Krystel By Kams Realtors
possession by Dec 2026 · Kams Realtors
Kshitij Eminence
declared completion Jun 2026 · Kshitij Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026