MahaRERA · the public record
KURLA LIG VIKRANT C.H.S LTD
KURLA · KONSHILA INFRASTRUCTURES PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Sep 2024
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800006042
Delivery and registration
When is the project declared for completion?
KURLA LIG VIKRANT C.H.S LTD is registered with MahaRERA as P51800006042 and the promoter has declared completion for 30 Sep 2024.
30 Sep 2024
declared completion
24months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800006042 |
| Registered on | 14 Aug 2017 |
| Promoter-declared completion | 30 Sep 2024 |
| Current status | Certificate Signed |
| Against today | about 24 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KURLA LIG VIKRANT C.H.S LTD record 29 quarterly progress reports since registration.
29quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for KURLA LIG VIKRANT C.H.S LTD in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| KURLA LIG VIKRANT CHS LTD | 1 | G+8 | 31 Jul 2018 |
Legal and disputes
What disputes are disclosed?
4 complaints are on the MahaRERA record for KURLA LIG VIKRANT C.H.S LTD, with orders passed in 4 of them.
4complaints
4with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000195248 | 10/01/2021 | Salman Akhtar Husain Batliwala vs Subodh Gite | order passed |
| CC006000000210010 | 12/02/2022 | M/s. Konshila Infrastructure Pvt. Ltd., vs Mr. Mohammed Eshan Gani Sayyed | order passed |
| CC006000000220837 | 11/05/2022 | KONSHILA INFRASTRUCTURE PRIVATE LIMITED vs Mr Abdul Nasir Khan and Mrs. Khadija Abdul Nasir Khan | order passed |
| CC006000000220859 | 11/05/2022 | KONSHILA INFRASTRUCTURE PRIVATE LIMITED vs Mr Abdul Nasir Khan and Mrs. Khadija Abdul Nasir Khan | order passed |
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Co Operative Court Mumbai | 81/17 | 2016 | Status Reply Of Defendants In Stay Application Of Petitioner |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Jul 2020 | Self certified copy of the permission / approval from the competent authority which is valid for a period which is longer than the proposed term of extension of the registration so |
| 31 Jul 2020 | 31 Jul 2020 | Respected Sir/Madam, With reference to the above cited subject, we regret to inform you that we have requested managing committee of society for getting application Let |
| 31 Jul 2020 | 30 Sep 2024 | In accordance with circular no 28, we hereby apply for extension of our project under order no. 40 in Format B. The project was delayed for reasons beyond our control on account of |
Location, Land & Connectivity
Located at KURLA, KURLA, Thane, Thane, 400070. Per the filed land record, the plot is bounded to the north by BUILDING NO 49, to the south by SLUM AREA, to the east by 40 METER WIDE ROAD and to the west by OPEN SCHOOL PLOT. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Bandra Kurla Complex (BKC) | 2 km |
| Chhatrapati Shivaji Int'l Airport | 3 km |
| Powai / Hiranandani business park | 6 km |
| Andheri MIDC / SEEPZ | 7 km |
| Lower Parel / Worli business district | 10 km |
| Nariman Point / Fort | 17 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.