MahaRERA Property Intelligence · Thane
P51700011246 · G B Road · promoter Laabh Buildwell
| MahaRERA registration | P51700011246 |
| Registered on | 31 Aug 2017 |
| Promoter-declared completion | 31 Dec 2025 |
| Current status | Certificate Signed |
| Against today | about 7 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Laabh Buildwell is the promoter of record on 9 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| BUILDING A | 1 | G+17 | - |
| BUILDING B | 1 | G+7 | - |
3 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000078275 | 27/02/2019 | SANKET PRABHAKAR YADAV vs LAABH BUILDWELL | order passed |
| CC006000000220855 | 17/04/2022 | KIRAJ ASHOK SHRIWARDHANKAR vs Laabh Buildwell | order passed |
| CC12503955 | 11/11/2025 | Laabh Gloria A wing CHS LTD Through its Secretary Ravi Ojha (society) vs LAABH BUILDWELL | pending / no order on file |
⚠ A co-operative housing society is the complainant here (Laabh Gloria A wing CHS LTD Through its Secretary Ravi Ojha). On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 29 May 2024 | 29 May 2024 | My project is already completed and only the OC is yet to be received For getting the OC I need the extension for the said project Also due to COVID Pandemic, the construction was |
| 30 May 2023 | 31 Dec 2025 | We have submitted an application (RERA Number P5170011246) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7(3) of the R |
Located at G B Road, Kasarvadavli, Thane, Thane, 400615. Per the filed land record, the plot is bounded to the north by SN 107, to the south by 20 M WIDE DP ROAD, to the east by SN 106 and to the west by 40 M WIDE DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 18 km |
| Andheri MIDC / SEEPZ | 19 km |
| Chhatrapati Shivaji Int'l Airport | 23 km |
| Bandra Kurla Complex (BKC) | 25 km |
| Lower Parel / Worli business district | 34 km |
| Nariman Point / Fort | 41 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in LAABH GLORIA?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026