Mumbai/Project record

MahaRERA · the public record

LALBAUG DARSHAN

KON · VISHAL R GROUP & ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700021729

Delivery and registration

When is the project declared for completion?

LALBAUG DARSHAN is registered with MahaRERA as P51700021729 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700021729
Registered on22 Jul 2019
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LALBAUG DARSHAN record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vishal Group Enterprises is the promoter of record on 99 projects registered with MahaRERA, 18 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

99projects

registered with MahaRERA

18flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LALBAUG DARSHAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A WING1G+4-
B WING1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KON, KALYAN BHIWANDI ROAD, Bhiwandi, Thane, 421311. Per the filed land record, the plot is bounded to the north by S NO 186, to the south by 20 W ROAD, to the east by S NO 187 and to the west by S NO 186. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kongaon

Namo Maxima
possession by Dec 2026 · Viren Kishor Jain
Shree Laxman Apartment
possession by Dec 2026 · Shri Gajanan Enterprises
Tahoora Complex
Not filing quarterly progress reports · possession by Dec 2026 · Shree Harekrishna Realtor
Atlantic
possession by Mar 2027 · Riddhi Siddhi Enterprises
Magus City Tower 1 Selene
possession by Apr 2027 · Magus Infratech Private Limited
SAI Darshan
possession by Apr 2027 · Trimurti Enterprises

Major developers building in Kongaon

Other RERA-registered projects in Thane

Lambodara Palace
declared completion Dec 2020 · Vighnaharta Enterprises
Landmark Aristo
possession by Dec 2030 · Landmark Lifestyle
Landscape Heritage Building NO 1
declared completion Mar 2020 · Landscape Infrastructure
Landscape Heritage Building NO 2
declared completion Dec 2022 · Landscape Infrastructure
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers
Larkins 315 Rio - B
possession by Dec 2028 · M/S Pushpak Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026