MahaRERA Property Intelligence · Thane

Larkins 315 Rio - B

P51700052258 · Panchpakhadi- Thane (W) · promoter Pushpak Developers

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationP51700052258
Registered on02 Aug 2023
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pushpak Developers is the promoter of record on 9 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+34.

BuildingWingsFloorsDeclared completion
Wing B1G+34-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Panchpakhadi- Thane (W), TPS-I, Panchpakhadi, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by DP Road, to the south by DP Road, to the east by Wing A Fio and to the west by Existing Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/S Pushpak Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every M/S Pushpak Developers project & its RERA track record →

Other flagged projects by M/S Pushpak Developers

M/S Pushpak Developers
Deregistered by MahaRERAThane
M/S Pushpak Developers
FlaggedThane

Other RERA-registered projects in Naupada

Veer Galaxy
possession by Jul 2026 · Yash Infra
Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty

Major developers building in Naupada

Other RERA-registered projects in Thane

Larkins Nest
declared completion Jun 2026 · Pride Property Developers
Lata CO Operative Housing Society Limited
possession by Dec 2027 · NYP Developers
Laukik Homes Green City Phase 1
possession by Jun 2027 · Laukik Homes
Laurel
declared completion Dec 2022 · Pacific Impressions
Lawate Heights
declared completion Mar 2026 · Shree Ganesh Developers
Laxman Residency
possession by Dec 2026 · Crystal Krishraj

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026