315 Avenue

Panchpakhadi · M/S PUSHPAK DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020863

Delivery and registration

When is the project declared for completion?

315 Avenue is registered with MahaRERA as P51700020863 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020863
Registered on15 May 2019
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 315 Avenue record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Pushpak Developers is the promoter of record on 9 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 315 Avenue in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
315 Avenue1G+1331 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Panchpakhadi, Panchpakhadi, Nr Gurukul Society, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by 12 MTR ROAD, to the south by SHIVNERI BUILDING, to the east by 6MTR ROAD and to the west by 12 MTR ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/S Pushpak Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every M/S Pushpak Developers project & its RERA track record →

Other flagged projects by M/S Pushpak Developers

M/S Pushpak Developers
FlaggedThane
M/S Pushpak Developers
FlaggedThane

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

36 Mansions A Wing
possession by Dec 2027 · Sri Lifespace
38 Buttercup
declared completion Apr 2022 · GUL Gianchand Vatiani
44 West
possession by Sep 2029 · Krystal Infra
67 Tenements, 9 Shops At Survey No.209,h.no.8,12 Near Building No.18,22 Vartaknagar,thane
declared completion Mar 2022 · Vivek Barve
9 Square
possession by Dec 2026 · Shivsai Homes Builders AND Developers LL
90 Degree Avenue
possession by Jan 2029 · Shree Tirupati Enterprises

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026