Mumbai/Project record

MahaRERA · the public record

LAVANYA APARTMENT

Boisar East · ROYAL INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000011698

Delivery and registration

When is the project declared for completion?

LAVANYA APARTMENT is registered with MahaRERA as P99000011698 and the promoter has declared completion for 31 Jan 2024.

31 Jan 2024

declared completion

32months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000011698
Registered on31 Aug 2017
Promoter-declared completion31 Jan 2024
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LAVANYA APARTMENT record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Royal Infra is the promoter of record on 182 projects registered with MahaRERA, 27 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

182projects

registered with MahaRERA

27flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LAVANYA APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
LAVANYA APARTMENT1G+4-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for LAVANYA APARTMENT, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260202706/04/2026Hussain Abbas Madarwala vs ROYAL INFRApending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Our project consist of 40 Flats out of which only 7 agreements were finalized and in further period no more flats sold due to which we faced insufficiency of funds for further comp
30 Apr 202031 Jul 2023Low Demand in Market only 9 flats sold out of 40 flats, need some time and 9 allottees are agree for the same.

Location, Land & Connectivity

Located at Boisar East, Village Betegoan, Boisar, Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by 19 DEGREE N - 72 DEGREE E, to the south by 19 DEGREE N - 72 DEGREE E, to the east by 19 DEGREE N - 72 DEGREE E and to the west by 19 DEGREE N - 72 DEGREE E. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~73 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ73 km
Powai / Hiranandani business park75 km
Chhatrapati Shivaji Int'l Airport78 km
Bandra Kurla Complex (BKC)80 km
Lower Parel / Worli business district88 km
Nariman Point / Fort95 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Royal Infra is the promoter on 4 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Royal Infra

Royal Infra
Not filing quarterly progress reportsPalghar

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

Laxmi APT
declared completion Dec 2023 · Rameshchandra Ramnidh Pandey
Laxmi Developers
declared completion Jul 2022 · Laxmi Developers
Laxmi Heights
possession by Dec 2027 · Janavi Builders & Developers
Laxmi Tower
possession by Dec 2030 · Shree Construction
Laxmi Tower, Building NO. 2
possession by Dec 2027 · Laxman Singh
Leisure Park
declared completion May 2026 · Anjali Anil Patil

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026