Mumbai/Project record

MahaRERA · the public record

LAXMI DEVELOPERS

JYOTI STOP · LAXMI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000028521

Delivery and registration

When is the project declared for completion?

LAXMI DEVELOPERS is registered with MahaRERA as P99000028521 and the promoter has declared completion for 31 Jul 2022.

31 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000028521
Registered on08 Mar 2021
Promoter-declared completion31 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LAXMI DEVELOPERS record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LAXMI DEVELOPERS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.

BuildingWingsFloorsDeclared completion
GREENLAND VILLA1G+031 Jan 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JYOTI STOP, VIRAR - ARNALA ROAD, Vasai, Palghar, 401302. Per the filed land record, the plot is bounded to the north by VIRAR ARNALA ROAD, to the south by HOUSE OF KUMAR VAZE, to the east by PROPERTY OF KUMAR VAZE and to the west by PROPERTY OF DAMODAR BHOIR. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Laxmi Developers is the promoter on 12 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Laxmi Developers project & its RERA track record →

Other flagged projects by Laxmi Developers

Other RERA-registered projects in Jyoti Stop

Raghu Leela
possession by Dec 2027 · P Kawali Builders

Other RERA-registered projects in Palghar

Laxmi Heights
possession by Dec 2027 · Janavi Builders & Developers
Laxmi Tower
possession by Dec 2030 · Shree Construction
Laxmi Tower, Building NO. 2
possession by Dec 2027 · Laxman Singh
Leisure Park
declared completion May 2026 · Anjali Anil Patil
Leona Residency D
declared completion Dec 2025 · Erral Poshan Furtado
Liberty Industrial Park
declared completion Jun 2025 · Gurunanak Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026