MahaRERA Property Intelligence · Thane

M P ELITE

P51700051122 · Kurla Camp Ulhasnagar · promoter Buildcon

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51700051122
Registered on30 May 2023
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 1 homes filed with MahaRERA, 0 are sold/booked and 1 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101312 sqft (29 sqm)-

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 1 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
M P Elite1G+6131 Dec 2024

Unit mix on the filing: 1 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kurla Camp Ulhasnagar, Kailash Colony, Ulhasnagar, Thane, 421005. Per the filed land record, the plot is bounded to the north by Adjacent Block No 961, to the south by CTS No 24659 Dev Prakash Apt, to the east by CTS No 24657 Pari Mahal Apt and to the west by D P Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Prem Nagar Tekdi

Devi Hills
possession by Dec 2026 · SAI RAM Developers
Hiltron Hills
possession by Dec 2027 · Hillview Realty
Kohinoor Pearl
possession by Mar 2028 · Real Infra Company
Devi Heights
declared completion Jun 2026 · Luxur AND Lavish Homes
Soham Residency
declared completion Mar 2026 · Soham Construction
Jhalak Paradise
Not filing quarterly progress reports · declared completion Dec 2025 · Jhalak Constructions

Other RERA-registered projects in Thane

M/S OM Shakti Swastik Co-Op Hsg Soc Ltd
declared completion Jun 2022 · M/S Sparsh Infra
M/s. Sadguru Narayan Maharaj Shree Gondekar CHS LTD-Namashree
possession by Mar 2027 · Nilpadma Developers
M/s. Shubham Karoti Complex Phase - I
declared completion Mar 2018 · M/s. Shubham Karoti Enterprises
M/s. Shubham Karoti Complex Phase - II
declared completion Dec 2018 · M/s. Shubham Karoti Enterprises
M/s. Shubham Karoti Complex Phase - III
declared completion Mar 2022 · M/s. Shubham Karoti Enterprises
M/s Simco Jyoti
declared completion Mar 2022 · Suresh Mithalal Jain

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026