Mumbai/Project record

MahaRERA · the public record

SHYAM AANGAN

Kurla Camp Road · SACHDEV DEVELOPERS (OPC) PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700047719

Delivery and registration

When is the project declared for completion?

SHYAM AANGAN is registered with MahaRERA as P51700047719 and the promoter has declared completion for 31 May 2026.

31 May 2026

declared completion

4months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700047719
Registered on21 Nov 2022
Promoter-declared completion31 May 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHYAM AANGAN record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Sachdev Developers (Opc) is the promoter of record on 8 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHYAM AANGAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SHYAM AANGAN1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 May 2026Project got delayed due to unavoidable reasons.

Location, Land & Connectivity

Located at Kurla Camp Road, Kurla Camp, Ulhasnagar, Thane, 421005. Per the filed land record, the plot is bounded to the north by Open Plot, to the south by Room No 1855 of Blk No C-928, to the east by Back of said property and to the west by Main Entrance of property and Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ulhasnagar 5

Devi Hills
possession by Dec 2026 · SAI RAM Developers
Hiltron Hills
possession by Dec 2027 · Hillview Realty
Kohinoor Pearl
possession by Mar 2028 · Real Infra Company
Devi Heights
declared completion Jun 2026 · Luxur AND Lavish Homes
Soham Residency
declared completion Mar 2026 · Soham Construction
Jhalak Paradise
Not filing quarterly progress reports · declared completion Dec 2025 · Jhalak Constructions

Other RERA-registered projects in Thane

Shyam B
possession by Dec 2028 · Raje Builders & Developers
Shyam Heritage
declared completion Oct 2024 · Vishnu Shyamlal Sachdev
Shyam Vatika
declared completion Jun 2024 · Mahesh Shamlal Sachdev
Siddham Heights
declared completion Dec 2025 · Bhoopendra Ghisulal Borana
Siddhashram CHS LTD
declared completion Oct 2018 · Standard Infrastructure
Siddheshwar
declared completion Dec 2023 · Siddheshwar Group

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026