Mumbai/Project record

MahaRERA · the public record

SIDDHASHRAM CHS LTD

NAUPADA · STANDARD INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Oct 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Oct 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700015588

Delivery and registration

When is the project declared for completion?

SIDDHASHRAM CHS LTD is registered with MahaRERA as P51700015588 and the promoter has declared completion for 01 Oct 2018.

01 Oct 2018

declared completion

95months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700015588
Registered on08 Mar 2018
Promoter-declared completion01 Oct 2018
Current statusCertificate Signed
Against todayabout 95 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIDDHASHRAM CHS LTD record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Standard Infrastructure is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIDDHASHRAM CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SIDDHASHRAM CHS LTD1G+801 Oct 2018

Legal and disputes

What disputes are disclosed?

16 complaints are on the MahaRERA record for SIDDHASHRAM CHS LTD, with orders passed in 16 of them.

16complaints

16with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000008984026/06/2019JAYWANT M BHOIR vs STANDARD INFRASTURCTUREorder passed
CC00600000019713606/06/2021Sidhashram Co-operative Housing Society Ltd (society) vs M/s Standard Infrastructureorder passed
CC00600000039732314/09/2023Sudhakar Anant Desai vs Standard Infrastructureorder passed
CC00600000039732614/09/2023Meena Mahajan vs Standard Infrastructureorder passed
CC00600000039732714/09/2023Madhura Chandrakant Joshi vs Standard Infrastructureorder passed
CC00600000039742414/09/2023Vikas Gopal Pathak vs Standard Infrastructureorder passed
CC00600000039740414/09/2023Snehal Pravin Joshi vs Standard Infrastructureorder passed
CC00600000039743114/09/2023Sudha Padmakar Shukla vs Standadrd Infrastructureorder passed
CC00600000039747514/09/2023Kunda Govind Deshpande vs Standard Infrastructureorder passed
CC1250233010/07/2025STANDARD INFRASTRUCTURE vs Siddhashram Co Op Housing Society Ltd (Society)order passed
CC1250233110/07/2025STANDARD INFRASTRUCTURE vs Siddhashram Co Op Housing Society Ltd (Society)order passed
CC1250233210/07/2025STANDARD INFRASTRUCTURE vs Siddhashram Co Op Housing Society Ltd (Society)order passed
CC1250233310/07/2025STANDARD INFRASTRUCTURE vs Siddhashram Co Op Housing Society Ltd (Society)order passed
CC1250233410/07/2025STANDARD INFRASTRUCTURE vs Siddhashram Co Op Housing Society Ltd (Society)order passed
CC1250233510/07/2025STANDARD INFRASTRUCTURE vs Siddhashram Co Op Housing Society Ltdorder passed
CC1250233610/07/2025STANDARD INFRASTRUCTURE vs Siddhashram Co Op Housing Society Ltd (Society)order passed

A co-operative housing society is recorded as the complainant (Sidhashram Co-operative Housing Society Ltd), and MahaRERA has passed an order.

Location, Land & Connectivity

Located at NAUPADA, GOKHALE ROAD, Mumbai City, Mumbai City, 400602. Per the filed land record, the plot is bounded to the north by PLOT NO 89A, to the south by PLOT NO 95, to the east by PLOT NO 90 and to the west by PLOT NO 93. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Siddheshwar
declared completion Dec 2023 · Siddheshwar Group
Siddheshwar Heights A Wing From 2nd TO 14th Floor
declared completion Jan 2025 · Shree JAI Malhar Enterprises
Siddhi
declared completion Mar 2026 · Fore Holdings
Siddhi Vinayak Residency
declared completion Jun 2023 · Rainbow Developers
Siddhivinayak Arcade
possession by Dec 2026 · Siddhivinayak Builders & Developers
Siddhivinayak Aura Building - 1
possession by May 2029 · Varadvinayak Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026