Mumbai/Project record

MahaRERA · the public record

SIDDHI VINAYAK RESIDENCY

NEXT TO DIVA VASAI RAILWAY LINE · RAINBOW DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700017031

Delivery and registration

When is the project declared for completion?

SIDDHI VINAYAK RESIDENCY is registered with MahaRERA as P51700017031 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700017031
Registered on04 Jul 2018
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIDDHI VINAYAK RESIDENCY record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rainbow Developers is the promoter of record on 16 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIDDHI VINAYAK RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
BUILDING A1G+1130 Jun 2022
BUILDING C1G+830 Jun 2022

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for SIDDHI VINAYAK RESIDENCY, with orders passed in 10 of them.

10complaints

10with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000030313621/10/2022RehanAnsari vs Rainbow Developersorder passed
CC00600000059157516/08/2024Rehan Ansari vs Rainbow Developersorder passed
CC00600000059157716/08/2024Rehan Ansari vs Rainbow Developersorder passed
CC00600000059157816/08/2024Rehan Ansari vs Rainbow Developersorder passed
CC00600000059157916/08/2024Rehan Ansari vs Rainbow Developersorder passed
CC00600000059158016/08/2024Rehan Ansari vs Rainbow Developersorder passed
CC00600000039678130/07/2023kanchan suraj khanna vs M/s. Rainbow Developersorder passed
CC1250407119/11/2025VISHAL RAJESH WAGHMARE vs RAINBOW DEVELOPERSorder passed
CC1250421328/11/2025SHRINIVAS CHANDRAYA KAMTAM vs shrinivas chandraya kamtamorder passed
CC1250421628/11/2025vilas viththal jadhav vs VILAS VITHTHAL JADHAVorder passed

Location, Land & Connectivity

Located at NEXT TO DIVA VASAI RAILWAY LINE, BHIWANDI OVALI ROAD, Bhiwandi, Thane, 421305. Per the filed land record, the plot is bounded to the north by BHIWANDI OVALI ROAD, to the south by DIVA VASAI RAILWAY LINE, to the east by BHIWANDI OVALI ROAD and to the west by BMC PIPELINE. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kamatghar

Shambhu Shankar Residency
possession by Dec 2026 · Vidisha Constructions
Shiv SAI Awas
possession by Dec 2026 · Vidisha Constructions
Shivam Residency Phase II
possession by Dec 2026 · Shivam Developers
Vighnaharta Apartment
possession by Jan 2027 · Vinayak Infrabuild
Varhaala Heights
possession by Mar 2028 · Sarvashiva Enterprises
SKY City
possession by Jun 2028 · Sunrise Realtors

Other RERA-registered projects in Thane

Siddhivinayak Arcade
possession by Dec 2026 · Siddhivinayak Builders & Developers
Siddhivinayak Aura Building - 1
possession by May 2029 · Varadvinayak Developers
Siddhivinayak Enclave
possession by Dec 2028 · Siddhi Developers
Siddhivinayak Height
declared completion Mar 2020 · Siddhivinayak Developers
Siddhivinayak Homes
possession by Dec 2026 · Siddhivinayak Builders AND Developers
Siddhivinayak Prasad CO-Op.housing Soc.ltd
possession by Dec 2026 · Shaurya Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026