Mumbai/Project record

MahaRERA · the public record

MAHATMA ENCLAVE

Thane · Mahatma Infrasturcture (India) LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700012653

Delivery and registration

When is the project declared for completion?

MAHATMA ENCLAVE is registered with MahaRERA as P51700012653 and the promoter has declared completion for 31 Dec 2020.

31 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700012653
Registered on07 Sep 2017
Promoter-declared completion31 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAHATMA ENCLAVE record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mahatma Infrasturcture (India) is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAHATMA ENCLAVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
MAHATMA ENCLAVE B WING1G+9-
MAHATMA ENCLAVE C AND D WING1G+530 Sep 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2019APPLIED FOR OCCUPANCY CERTIFICATE FOR THIS WE REQUIRED THE PROJECT EXTENSION FOR ONE YEAR .
30 Sep 201931 Dec 2020Mahatma Enclave Old SNo 325 New SNo 31 Hissa No 4,7,15,16 registered with the regulatory authority vide project registration certificate bearing No. P51700012653 , which ex

Location, Land & Connectivity

Located at Thane, Thane, 401105. Per the filed land record, the plot is bounded to the north by OLD SNO 325 HNO 5, to the south by D P ROAD, to the east by SNO NO 325 HNO 9 and to the west by MIRA BHAYANDER SPORTS COMPLEX. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ17 km
Powai / Hiranandani business park19 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mahatma Infrasturcture LLP is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Bhayander East

Gayatri Elegance
possession by Dec 2026 · Gayatrikripa Developers Private Limited
Basera Heights
possession by Dec 2026 · Kamruddin Hasmullah Siddique
Durga Enclave
possession by Dec 2026 · Anmol Developers
Ranuja Ramdev C Type
possession by Dec 2026 · Ranuja Ramdev C Type
Surya Heritage A
possession by Dec 2026 · Arun Construction CO
The Pentagon
possession by Dec 2026 · Anjani Kumar Realty Private Limited

Other RERA-registered projects in Thane

Mahatma Residency
declared completion Dec 2024 · Rajman Rajpat Yadav
Mahaveer Horizon Wing A AND Wing B
possession by Dec 2028 · Mahaveer Infrastructure PVT LTD
Mahaveer Signature
possession by Dec 2031 · Mahaveer Traders
Mahavir Arcade
declared completion Jul 2023 · Navin Kamlaprasad Singh
Mahavir Bliss
possession by Dec 2026 · M/s. Shivshakti Engineers
Mahavir Breeze Phase 1
declared completion Dec 2024 · Damji Shamji Realty Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026