Mumbai/Project record

MahaRERA · the public record

MAJESTIC HEIGHTS

Thane · MAJESTIC INFRA PROJECTS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700008183

Delivery and registration

When is the project declared for completion?

MAJESTIC HEIGHTS is registered with MahaRERA as P51700008183 and the promoter has declared completion for 30 Mar 2021.

30 Mar 2021

declared completion

66months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700008183
Registered on18 Aug 2017
Promoter-declared completion30 Mar 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAJESTIC HEIGHTS record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Majestic Infra Projects is the promoter of record on 29 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

29projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAJESTIC HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+30.

BuildingWingsFloorsDeclared completion
MAJESTIC HEIGHTS1G+30-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for MAJESTIC HEIGHTS, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039737106/09/2023Shaista Farooque Zamane vs Imtiyaz Gulamnbi Pirzadaorder passed
CC1260102125/02/2026Majestic Heights Cooperative Housing Society Ltd (society) vs MAJESTIC INFRA PROJECTS PRIVATE LIMITEDpending / no order on file

A co-operative housing society is recorded as the complainant (Majestic Heights Cooperative Housing Society Ltd).

Location, Land & Connectivity

Located at Thane, Thane, 400706. Per the filed land record, the plot is bounded to the north by LANDMARK CHS LTD, to the south by GURU BHAVAN AND CTS NO 9, to the east by JANKI NIWAS AND 11 M WIDE ROAD and to the west by 9 M WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Bandra Kurla Complex (BKC)16 km
Chhatrapati Shivaji Int'l Airport17 km
Andheri MIDC / SEEPZ19 km
Lower Parel / Worli business district20 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nerul

Cyber Code
possession by Sep 2026 · Greenscape Realty
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
possession by Dec 2026 · Emperia Projects
Plan I
possession by Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
possession by Dec 2026 · Regency INC
Sawan Serenity
possession by Dec 2026 · Shree Sawan Buildcon

Other RERA-registered projects in Thane

Makarand-Bank OF Baroda Employees CO-Operative Housing Society Limited
declared completion Jun 2022 · Prime Realtors
Malhar Enclave
possession by May 2028 · SM Enterprises
Mali Avenue
possession by Dec 2026 · Mali Infra
Mali Pinnacle
possession by Jan 2027 · Mali Infra
Malshej Green
declared completion Dec 2024 · Green Space Real Tech
Mamta 1351
possession by Dec 2026 · Patil Group Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026