MahaRERA Property Intelligence · Mumbai City

MANGESH RESIDENCY

P51900052706 · DADAR WEST · promoter Tendulkar And Associates

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51900052706
Registered on22 Sep 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tendulkar And Associates is the promoter of record on 12 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~78.6% of the estimated project cost incurred as of the last certificate (₹53.18 Cr spent against a ₹67.64 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 31 homes filed with MahaRERA, 4 are sold/booked and 27 remain available (~13% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹7.07 Cr in agreement value so far. Of that, ₹3.04 Cr (~43%) is already collected, ₹3.39 Cr receivable — a read on how far along these sales really are. Note: the project registers 51 homes in total, but this sold/unsold inventory filing covers only 31 of them — the other 20 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 101001470 sqft (43.66 sqm)₹1.07 Cr
Floor 101003470 sqft (43.66 sqm)₹1.07 Cr
Floor 111101470 sqft (43.66 sqm)₹1.07 Cr
Floor 111103470 sqft (43.66 sqm)₹1.07 Cr
Floor 121201470 sqft (43.66 sqm)₹1.07 Cr
Floor 121203470 sqft (43.66 sqm)₹1.07 Cr
Floor 131301470 sqft (43.66 sqm)₹1.07 Cr
Floor 131302470 sqft (43.66 sqm)₹1.07 Cr
Floor 131303470 sqft (43.66 sqm)₹1.07 Cr
Floor 141403190 sqft (17.62 sqm)₹43.21 Lakh
Floor 151501470 sqft (43.66 sqm)₹1.07 Cr
Floor 161601940 sqft (87.33 sqm)₹2.14 Cr
Floor 161602470 sqft (43.66 sqm)₹1.07 Cr
Floor 171701940 sqft (87.33 sqm)₹2.14 Cr
Floor 171702470 sqft (43.66 sqm)₹1.07 Cr
Floor 181801940 sqft (87.33 sqm)₹2.14 Cr
Floor 181802470 sqft (43.66 sqm)₹1.07 Cr
Floor 191901940 sqft (87.33 sqm)₹2.14 Cr
Floor 191902470 sqft (43.66 sqm)₹1.07 Cr
Floor 202001940 sqft (87.33 sqm)₹2.14 Cr
Floor 202002470 sqft (43.66 sqm)₹1.07 Cr
Floor 212101940 sqft (87.33 sqm)₹2.14 Cr
Floor 212102470 sqft (43.66 sqm)₹1.07 Cr
Floor 222201940 sqft (87.33 sqm)₹2.14 Cr
Floor 222202470 sqft (43.66 sqm)₹1.07 Cr
Floor 4401470 sqft (43.66 sqm)₹1.07 Cr
Floor 8801485 sqft (45.06 sqm)₹1.11 Cr

⚠ The inventory filing also declares: 1 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22 and 51 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
MANGESH RESIDENCY1G+2251-

Unit mix on the filing: 51 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at DADAR WEST, SARASWATIBAI JOSHI MARG, Ward GNorth, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by RATNAKAR BHYANDARKAR MARG, to the south by SARASWATIBAI JOSHI MARG, to the east by SARASWATIBAI JOSHI MARG and to the west by F P 350 NAMINATH APARTMENT. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar West

Arihant Tower
possession by Sep 2026 · Mehta Developers
Palette
possession by Sep 2026 · Suraj Estate Developers LTD
Vijayshree
possession by Sep 2026 · Sugee Eighteen Developers LLP
Yash Trinity
possession by Sep 2026 · Bhalchandra Vinayak Wadnerkar
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
possession by Dec 2026 · Nascent Developers

Major developers building in Dadar West

Other RERA-registered projects in Mumbai City

Mangirish
declared completion Jun 2022 · Accord Estates PVT LTD
Manikya
possession by Mar 2029 · Aryaman Enterprises
Mansion 835
possession by Dec 2027 · Rajadhiraj Construction LLP
Maple Heights
declared completion Jun 2026 · M/s ISD Infrastructure
Marathon Futurex 1
declared completion Jun 2021 · Marathon Nextegen Realty LTD
Marathon Futurex 2
declared completion Jun 2022 · Marathon Realty PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026