Mumbai/Project record

MahaRERA · the public record

Matrix Estella

Nerul · MATRIX SUPERSTRUCTURES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

97units filed as unsoldInventory · 20 September 2026
31 Dec 2032declared completionMahaRERA registration · read 02 Jul 2026
33registered unitsMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2032

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1330002503040

Delivery and registration

When is the project declared for completion?

Matrix Estella is registered with MahaRERA as PR1330002503040 and the promoter has declared completion for 31 Dec 2032.

31 Dec 2032

declared completion

75months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1330002503040
Registered on24 Mar 2026
Promoter-declared completion31 Dec 2032
Current statusCertificate Signed
Against today75 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Matrix Estella record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026

  • Filing progress reports — 1 quarterly progress report on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Matrix Superstructures is the promoter of record on 49 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

49projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Construction

How much construction cost has been reported?

In Matrix Estella, ₹1.25 Cr of a declared ₹115.00 Cr estimated project cost is reported as incurred, about 1.1%, as at the last certified filing with MahaRERA.

1.1%

₹1.25 Cr

of ₹115.00 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 02 Jul 2026

Sales

How much has actually been sold?

In Matrix Estella, 6 of 108 homes filed with MahaRERA are recorded as sold or booked (2 with registered agreements and 4 booked), about 6%, and 102 remain available.

6%sold

6 of 108 homes

₹6.45 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹46.48 Lakh (about 7%) is recorded as collected and ₹5.98 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

What buyers actually paid: across 6 registered agreements, the effective carpet rate is ₹15,631/sqft, with eight in ten falling between ₹15,618 and ₹18,011 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 48 reserved.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 11 homes carry one, and 97 of the 156 are recorded unsold. Since we started watching this ledger, 9 homes have moved out of the unsold list, most recently on 04 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
Flat No 601662 sqftRs 1.0350 cr typical, over Rs 1.0150 cr to Rs 1.1500 cr6 filed on this stack, floors 6–8

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Matrix Estella, 12 of the 97 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 96 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 33 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Matrix Estella3G+833-

Unit mix on the filing: 116 residential and 40 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Nerul, Nerul, Thane, Thane, 400706. Per the filed land record, the plot is bounded to the north by 15 Mtr Wide Road, to the south by Plot No -56 and 60, to the east by Proposed 15 Mtr Wide Road and to the west by Proposed 15 Mtr Wide Road . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Bandra Kurla Complex (BKC)17 km
Chhatrapati Shivaji Int'l Airport18 km
Andheri MIDC / SEEPZ20 km
Lower Parel / Worli business district21 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nerul

Cyber Code
possession by Sep 2026 · Greenscape Realty
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
possession by Dec 2026 · Emperia Projects
Plan I
possession by Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
possession by Dec 2026 · Regency INC
Sawan Serenity
possession by Dec 2026 · Shree Sawan Buildcon

Other RERA-registered projects in Thane

Matrix Imperial
possession by Dec 2028 · Matrix Lifestyle
Matru Mandir
possession by Dec 2026 · Parnad Anil Gupte
Matrukrupa Co-Operative Housing Society Ltd
possession by Dec 2027 · Shree Ganesh Krupa Builders And Develope
Mauli Angan
declared completion Mar 2025 · Mauli Enterprises
Mauli Krupa
declared completion Aug 2018 · Vighnesh Constructions
Mauli Madhusudhan
declared completion Dec 2025 · Rameshwar Yashwant Patil

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026