Mumbai/Project record

MahaRERA · the public record

Meridia

Kurla West · Accord Builders

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009440

Delivery and registration

When is the project declared for completion?

Meridia is registered with MahaRERA as P51800009440 and the promoter has declared completion for 30 Oct 2021.

30 Oct 2021

declared completion

59months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009440
Registered on22 Aug 2017
Promoter-declared completion30 Oct 2021
Current statusCertificate Signed
Against todayabout 59 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Meridia record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Accord Builders is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Meridia in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Meridia - 42 Units as per Apartment Type1G+1731 Oct 2020

Legal and disputes

What disputes are disclosed?

22 complaints are on the MahaRERA record for Meridia, with orders passed in 21 of them.

22complaints

21with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002280909/01/2018Molly Kapoor vs Babu Lal jiorder passed
CC00600000005664520/10/2018Kamal Kishore Uniyal vs Accord buildersorder passed
CC00600000008988902/07/2019Meraj Ali Mashoor Ali Khan vs Accord Buildersorder passed
CC00600000008998927/07/2019Alok Sanghi vs Accord Buildersorder passed
CC00600000010040216/09/2019Mateena Ayaz Merchant vs Omkar realtor / accord buildersorder passed
CC00600000010048409/09/2019Ravindra Mangal vs Accord Buildersorder passed
CC00600000011077406/09/2019Amit Dua and Anju Dua vs Omkar Realtors & Developers through SPV-Accord Buildersorder passed
CC00600000011086510/09/2019RENU CHAUDHARY vs Accord Buildersorder passed
CC00600000016129921/10/2019Natalia Bhatia vs Accord Buildersorder passed
CC00600000019475903/11/2020Natalia Bhatia vs Accord Buildersorder passed
CC00600000019580812/02/2021Rahul Kalyan Raghuwanshi vs M/s Accord Buildersorder passed
CC00600000019356012/08/2020Chandan Kumar vs Accord Builders LLPorder passed
CC00600000019376621/09/2020VIDYA HEGDE vs ACCORD BUILDERSorder passed
CC00600000019378620/08/2020Deepak Sadanand Neroorkar vs Accord Developersorder passed
CC00600000019488711/11/2020Sanchita Ghosh vs Accord Developersorder passed
CC00600000019598310/02/2021Kanchan Parshuram Dholam vs ACCORD BUILDERSorder passed
CC00600000019614326/02/2021Rahul Kalyan Raghuwanshi vs Accord Buildersorder passed
CC00600000019698812/05/2021Rohit Sharma vs M/s. Accord Buildersorder passed
CC00600000049038907/05/2024Vaibhav Singh vs ACCORD BUILDERSorder passed
CC00600000058089324/06/2024Accord Builders vs Ravindra Mangalorder passed
CC00600000058089624/06/2024Accord Builders vs Amit Duaorder passed
CC1240097302/12/2024MAHESH SURESH KHAMKAR vs Accord Builderspending / no order on file

Location, Land & Connectivity

Located at Kurla West, Ward FNorth, Mumbai City, 400070. Per the filed land record, the plot is bounded to the north by DP Road, to the south by BMC Buildings, to the east by Rehab A and to the west by HP Keluskar Marg. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Accord Builders is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Kurla West

Yojan One
possession by Sep 2026 · Meru Realty LLP
Imperial Heights
possession by Nov 2026 · Sumukha Realtors
Buddha Vihar CHS LTD
possession by Dec 2026 · M/S Regal Builders AND Developers
Khaliliya Complex
possession by Dec 2026 · Dani Builders AND Developers
Mantri Business Plaza
possession by Dec 2026 · Mantri Brothers
Rehmaniya Apartments
possession by Dec 2026 · S & S Enterprises

Major developers building in Kurla West

Other RERA-registered projects in Mumbai Suburban

Meridian Court 1
possession by Dec 2027 · Vijaykamal Properties Pvt Ltd
Meridian Courts Tower 2
declared completion Dec 2024 · Vijaykamal Properties Pvt Ltd
Merushikhar
declared completion Mar 2026 · Savvy Infrastructure Private Limited
Mesacon Bliss
possession by May 2028 · Vikram Rashmikant Mehta
Mesacon Crown
possession by Jun 2027 · Mesacon Spaces LLP
Mesacon Greens
possession by Jun 2027 · Mesacon Spaces LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026