Mumbai/Project record

MahaRERA · the public record

METRO HIGHLAND - PHASE II

CHIKHALOLI · METRO DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700024041

Delivery and registration

When is the project declared for completion?

METRO HIGHLAND - PHASE II is registered with MahaRERA as P51700024041 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

3months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700024041
Registered on16 Jan 2020
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 3 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for METRO HIGHLAND - PHASE II record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Metro Developers is the promoter of record on 79 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

79projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for METRO HIGHLAND - PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
R11G+830 Jun 2025
R21G+830 Jun 2025
R31G+830 Jun 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The Court Of Civil Judge S D Kalyan144/20132013Matter Is Subjudice
The Court Of Civil Judge S D Kalyan244/20132013Matter Is Subjudice
The Court Of Civil Judge S D Kalyan44/20182018Matter Is Subjudice
The Court Of Joint Civil Judge S D Kalyan265/20182018Matter Is Subjudice

Location, Land & Connectivity

Located at CHIKHALOLI, CHIKHALOLI ROAD, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by S NO 131, to the south by 18 MTR WIDE ROAD, to the east by S NO 128 H NO 1 PT and to the west by 12 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Metro Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Metro Developers

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Metro Hive D-1
possession by Dec 2026 · Vihang Infrastructure PVT LTD
Metro Imperial
possession by Dec 2028 · Pragati Combines
Metro Luxuria
possession by Dec 2027 · Nivara Engineers
Metro Majestic
declared completion Nov 2024 · Nakshatra Builders
Metro Regalia
possession by Dec 2027 · Shree Ashtavinayak Enterprises
Metropolis - Aquaris Phase 2
declared completion Sep 2025 · Anant Square

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026