MahaRERA Property Intelligence · Thane

MIRAYA BUSINESS HUB

P51700055878 · MAJIWADE · promoter Mextech Property Developers

Certificate SignedDue 15 Dec 2028

Delivery & Registration

MahaRERA registrationP51700055878
Registered on29 Apr 2024
Promoter-declared completion15 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mextech Property Developers is the promoter of record on 4 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~38.9% of the estimated project cost incurred as of the last certificate (₹52.45 Cr spent against a ₹134.81 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 144 homes filed with MahaRERA, 79 are sold/booked (68 with registered agreements + 11 booked) and 65 remain available (~55% sold) — selling steadily. Buyers have committed ₹156.81 Cr in agreement value so far. Of that, ₹82.98 Cr (~53%) is already collected, ₹79.39 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 79 registered agreements, the effective carpet rate is ₹17,332/sqft (typical range ₹14,423–₹27,454) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25 and 144 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building No-2 Commercial1G+25144-

Unit mix on the filing: 144 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MAJIWADE, SECTOR 4, Ward GSouth, Mumbai City, 400601. Per the filed land record, the plot is bounded to the north by 20M WIDE ROAD, to the south by NEELKANTH PALM COMPLEX, to the east by RAJESH LIFESTYLE AND ORION BUSINESS PARK and to the west by ENTRANCE ROAD OF NEELKANTH PALMS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mextech Property Developers LLP is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Mextech Property Developers LLP

Mextech Property Developers LLP
FlaggedThane
Mextech Property Developers LLP
FlaggedThane
Mextech Property Developers LLP
FlaggedThane

Other RERA-registered projects in Thane

Nandigram
possession by Jul 2026 · Yogesh Kishor Mahajan
Embassy One Thane - 1A 1B 1C
possession by Aug 2026 · Tapir Constructions Limited
Aurum
possession by Sep 2026 · Shree GHP Housing
Avesa
possession by Oct 2026 · Jagdale Infrastructure Pvt. Ltd.
Ramashankar CHS LTD
possession by Oct 2026 · SAI Prasad Builders AND Developers
Bhavana Apartment CHS
possession by Nov 2026 · Shree Infra

Major developers building in Thane

Other RERA-registered projects in Thane

Miraya Divine
possession by Dec 2029 · Mextech Property Developers LLP
Miraya Trinity - Eternity
possession by Dec 2029 · Mextech Property Developers LLP
Miraya Trinity - Serenity
possession by Dec 2029 · Mextech Property Developers LLP
Mitasha Avish Agrawal
declared completion Oct 2020 · Mitasha Avish Agrawal
Mlcp 3 Retail Shops
declared completion Dec 2024 · Lodha Developers Limited
MM Valley A-1
declared completion Dec 2025 · Alfa Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.