Mohak City Florence

P99000011207 · promoter Enterprises

Certificate SignedDue 30 Apr 2022

Delivery & Registration

MahaRERA registrationP99000011207
Registered on31 Aug 2017
Promoter-declared completion30 Apr 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
FLORENCE1G+730 Apr 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Apr 202230 Oct 2021Applied for OC at VVCMC

Location, Land & Connectivity

Located at Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by 19448393N72814515E, to the south by 19449633N72814252E, to the east by 19448744N72813756E and to the west by 19449335N72814994E. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ35 km
Powai / Hiranandani business park37 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)42 km
Lower Parel / Worli business district50 km
Nariman Point / Fort58 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar East

Gajanan Residency
possession by Aug 2026 · Pranita Pankaj Thakur
Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Devi Krupa
possession by Dec 2026 · Vira Links LLP
Jivdani Mauli
Not filing quarterly progress reports · possession by Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon

Other RERA-registered projects in Palghar

Mohak Garden City
possession by May 2031 · VMS Enterprises
Mohak House No.3 A Wing
declared completion Dec 2022 · V.s. Enterprises
Mohak Oyster Living
declared completion Jun 2023 · Oyster Corporation
Mohan Mansion
declared completion Mar 2021 · Shreeji Realtors
Momin Heights
possession by Dec 2026 · A-99 Developers
Monarch
declared completion Jan 2026 · Sadhbav Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026