MORAJ MAA SHRISHTI

P52000000480 · Lowjee · promoter Moraj Infratech Private

Certificate SignedDue 18 Dec 2018

Delivery & Registration

MahaRERA registrationP52000000480
Registered on18 Jul 2017
Promoter-declared completion18 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Moraj Infratech Private is the promoter of record on 176 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
wing B1G+718 Dec 2018
wing A proposed1-18 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Lowjee, chinchavli, Thane, Thane, 410203. Per the filed land record, the plot is bounded to the north by CTSNO-1113 AND CTS NO-1086, to the south by CTSNO-1112 1117 AND CTS NO-1105, to the east by PUBLIC ROAD and to the west by CTSNO-1114 AND CTS NO-1115. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~56 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort55 km
Bandra Kurla Complex (BKC)56 km
Powai / Hiranandani business park56 km
Lower Parel / Worli business district57 km
Chhatrapati Shivaji Int'l Airport58 km
Andheri MIDC / SEEPZ60 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Moraj Infratech Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Moraj Infratech Private Limited

Moraj Infratech Private Limited
FlaggedThane

Other RERA-registered projects in Khopoli

Daata Eklavya Building A & B
possession by Aug 2026 · Daata Builders And Developers Private Li
Krishna Valley - Phase 3
possession by Aug 2026 · Prishti Venture Private Limited
Sanskruti
possession by Sep 2026 · Sandip Shankar Patil
Amansara Earthstar
possession by Nov 2026 · SVB Lifespaces LLP
Amansara Earthstar PH
possession by Nov 2026 · SVB Lifespaces LLP
Riddhi Siddhi Complex
Not filing quarterly progress reports · possession by Dec 2026 · Riddhi Siddhi Developers

Major developers building in Khopoli

Other RERA-registered projects in Raigarh

Moraj MAA Smriti
declared completion Dec 2021 · Moraj Building Concepts Private Limited
Moral Orchid
declared completion Apr 2023 · Moral Infra
Moreshwar Apartment
declared completion Sep 2024 · Vishal Dilip Doshi
Moreshwar Height
possession by Dec 2026 · Diya Enterprises
Moreshwar Residency
declared completion Sep 2022 · Kishor Shivdas Gowari
Moreshwar Residency
declared completion Dec 2024 · Sagar Moreshwar Koli

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026