MahaRERA Property Intelligence · Raigarh

ASPIRE GREEN

P52000023085 · KHOP0LI · promoter Shriram Properties

Certificate SignedDue 31 Jul 2023

Delivery & Registration

MahaRERA registrationP52000023085
Registered on29 Nov 2019
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
ASPIRE GREEN1G+331 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KHOP0LI, CHICHAVALI SHEIKIN, Panvel, Raigarh, 410203. Per the filed land record, the plot is bounded to the north by 24 M WIDE ROAD, to the south by CTS NO 1134, to the east by CTS NO 1132 and to the west by CTS NO 1150. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Shriram Homebuild Developers LLP project & its RERA track record →

Other RERA-registered projects in Khopoli

Daata Eklavya Building A & B
possession by Aug 2026 · Daata Builders And Developers Private Li
Krishna Valley - Phase 3
possession by Aug 2026 · Prishti Venture Private Limited
Sanskruti
possession by Sep 2026 · Sandip Shankar Patil
Amansara Earthstar
possession by Nov 2026 · SVB Lifespaces LLP
Amansara Earthstar PH
possession by Nov 2026 · SVB Lifespaces LLP
Riddhi Siddhi Complex
Not filing quarterly progress reports · possession by Dec 2026 · Riddhi Siddhi Developers

Major developers building in Khopoli

Other RERA-registered projects in Raigarh

Aspire Park
declared completion May 2022 · Aspire Buildcon
Aspire Swagat
declared completion Sep 2024 · Aspire Developers
Aster
declared completion Jun 2022 · Walmik Raghunath Khairnar
Aster
possession by Dec 2031 · Persipina Developers Private Limited
Astha Avana
declared completion Jun 2026 · Anand Chandanmalji Soni HUF
Astitwa
possession by Dec 2027 · Butala & Shet Assiocates LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026