Mumbai/Project record

MahaRERA · the public record

MORESHWAR HEIGHTS

Palghar · PATIL ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000009662

Delivery and registration

When is the project declared for completion?

MORESHWAR HEIGHTS is registered with MahaRERA as P99000009662 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000009662
Registered on22 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MORESHWAR HEIGHTS record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MORESHWAR HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
MORESHWAR HEIGHTS1G+4-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for MORESHWAR HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250012613/01/2025PRASAD SHANKAR KOMNAK vs PATIL ASSOCIATESorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020PROJECT DELAY DUE TO GETTING REVISED C.C. AND DELAY DUE TO ELECTRICAL & PLUMBING CONTRACTORS

Location, Land & Connectivity

Located at Vasai, Palghar, 401303. Per the filed land record, the plot is bounded to the north by OPEN LAND, to the south by 20W D P ROAD, to the east by EXISTING ROAD and to the west by OPEN LAND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~29 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ29 km
Powai / Hiranandani business park31 km
Chhatrapati Shivaji Int'l Airport34 km
Bandra Kurla Complex (BKC)36 km
Lower Parel / Worli business district44 km
Nariman Point / Fort52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Patil Associates is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Patil Associates

Patil Associates
Past its declared completion dateThane

Other RERA-registered projects in Virar West

Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers
Sugandhi Square
possession by Dec 2026 · R. N. Realty
Vitthal Haven
possession by Dec 2026 · Sushila Builders & Developers

Other RERA-registered projects in Palghar

Moreshwar Niwas
declared completion Dec 2025 · Shriya Builders & Land Developers
Morya Heights
possession by Dec 2030 · Not Available
Mota Enclave
declared completion Jan 2021 · Mota Realtors LLP
Mother Vailankanni Apartment
possession by Dec 2027 · Satyesh Dattaray Nikam
Moti Green Park
declared completion Nov 2023 · Balaji Enterprises
Mrida Innovista Homes
possession by Mar 2031 · Nine Megacorp Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026