Morya Garden
Murbad · Sumit Developers
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Apr 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700023720
Delivery and registration
When is the project declared for completion?
Morya Garden is registered with MahaRERA as P51700023720 and the promoter has declared completion for 30 Apr 2027.
30 Apr 2027
declared completion
7months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700023720 |
| Registered on | 02 Jan 2020 |
| Promoter-declared completion | 30 Apr 2027 |
| Current status | Certificate Signed |
| Against today | 7 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Morya Garden record 27 quarterly progress reports since registration.
27quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Sumit Developers is the promoter of record on 44 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
44projects
registered with MahaRERA
7flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Morya Garden in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Building A | 1 | G+7 | 30 Apr 2023 |
| Building B | 1 | G+8 | 30 Apr 2023 |
| Building C | 1 | G+4 | 30 Apr 2023 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Apr 2027 | 1. Revision of Sanctioned Plans & Increased Scope: The project was initially envisioned and approved as a Ground + 6 floor structure. However, to optimize the land potential and me |
Location, Land & Connectivity
Located at Murbad, Dudhale Pada Road, Thane, Thane, 421401. Per the filed land record, the plot is bounded to the north by Existing Road, to the south by Lake, to the east by Existing Road and to the west by School. These are the boundaries as recorded in the filed land record.