Plotted Development Intelligence · Raigarh

Mount View - I

P52000033467 · Majare Jambulpada · promoter Ranjit Ramesh Pradhan

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP52000033467
Registered on22 Feb 2022
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ranjit Ramesh Pradhan is the promoter of record on 3 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Majare Jambulpada, Majare Jambulpada, Panvel, Raigarh, 410205. Per the filed land record, the plot is bounded to the north by Adj Gut No-200, to the south by Existing Village Road, to the east by Adj Gut No-327 and Adj Gut No-328 and to the west by Adj Gut No-196. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pali

Shubham Residency
possession by Oct 2026 · G D Jain Infra Projects
Annaprabha Complex
possession by Dec 2026 · Kishor Prabhakar Dandekar
City Of Music Phase III
possession by Dec 2026 · Nirvana Leisure Realty
City OF Music Phase IV
possession by Dec 2026 · Nirvana Leisure Realty
Joy Villa Phase-I
possession by Dec 2026 · Sadanand Laxmanrao Patil
Kenisha Resort Residences
possession by Dec 2026 · Kpin Real Estate Ventures

Other RERA-registered projects in Raigarh

Mount Ville
possession by Dec 2026 · M/S Samvid Life Spaces
Mountain Sapphire
possession by Dec 2028 · Trident Developers
Mountain View Residency 1
declared completion Mar 2025 · Immaculate Developers
Mountain View Residency 2
possession by Mar 2027 · Immaculate Developers
Mountain Villa
declared completion Apr 2023 · Sap Magic Developers Private Limited
MP Arena
declared completion Dec 2022 · MP Buildcon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026