MahaRERA Property Intelligence · Thane

N G CANARY PHASE II

P51700018931 · Ghodbunder · promoter Rna Builders (Ng)

Certificate SignedDue 29 Jun 2022

Delivery & Registration

MahaRERA registrationP51700018931
Registered on17 Dec 2018
Promoter-declared completion29 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
N G CANARY C1G+930 Jun 2020
N G CANARY D1G+930 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Jun 202229 Dec 2021We RNA Builders had registered our project N G Canary Phase 2 vide project registration number P51700018931 On 17/12/2018. Due to Covid 19 Pandemic our project cycle was disturbed

Location, Land & Connectivity

Located at Ghodbunder, Ghodbunder, Mumbai City, Mumbai City, 401104. Per the filed land record, the plot is bounded to the north by RAJ REALTY HSG SOCIETY, to the south by MUNICIPAL D P ROAD, to the east by MUNICIPAL NALA N G PARADISE and to the west by HATKESH ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

RNA Builders is the promoter on 24 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every RNA Builders project & its RERA track record →

Other flagged projects by RNA Builders

Other RERA-registered projects in Kashimira

SAI Enclave Wing B
possession by Dec 2026 · Mehta Realty
Meera Queen
possession by Dec 2028 · Not Available
Forest Vista
possession by Dec 2036 · Kashimira Ceramic Products LLP
Skywards Regency
declared completion Dec 2025 · Skywards Vision Developers
Westin Darvesh Horizon
declared completion Dec 2025 · Darvesh Properties Private Limited
Swapnalok Residency Phase II
declared completion Dec 2024 · Ashapura Builders & Developers

Other RERA-registered projects in Thane

N G Diamond Hill A Phase III
declared completion Dec 2024 · RNA Builders
N G Diamond Hill B Phase I
declared completion Dec 2021 · RNA Builders
N G Diamond Hill C Phase IV
declared completion Dec 2024 · RNA Builders
N G Diamond Hill D Phase II
declared completion Dec 2022 · RNA Builders
N G Grand Empire Phase I
possession by Dec 2026 · RNA Builders
N G Grand Empire Phase II
possession by Dec 2028 · RNA Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026