MahaRERA Property Intelligence · Thane

RUHEENA APPARTMENT

P51700013178 · Mira Road · promoter Sairajdevelop

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700013178
Registered on15 Sep 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sairajdevelop is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
RUHEENA APPARTMENT A B C WING1G+830 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Mira Road, Western PK Road, Thane, Thane, 401104. Per the filed land record, the plot is bounded to the north by SNO 16, to the south by 15 MTR DP ROAD, to the east by SNO 154 and to the west by SNO 98 15MTR D P ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ16 km
Powai / Hiranandani business park17 km
Chhatrapati Shivaji Int'l Airport20 km
Bandra Kurla Complex (BKC)23 km
Lower Parel / Worli business district31 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sairajdevelop is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sairajdevelop

Other RERA-registered projects in Kashimira

SAI Enclave Wing B
possession by Dec 2026 · Mehta Realty
Meera Queen
possession by Dec 2028 · Not Available
Forest Vista
possession by Dec 2036 · Kashimira Ceramic Products LLP
Skywards Regency
declared completion Dec 2025 · Skywards Vision Developers
Westin Darvesh Horizon
declared completion Dec 2025 · Darvesh Properties Private Limited
Swapnalok Residency Phase II
declared completion Dec 2024 · Ashapura Builders & Developers

Other RERA-registered projects in Thane

Rukmani Residency
possession by Dec 2027 · Clay Nest Developers
Rukmini Garden Building No 2
declared completion Dec 2021 · Maruti Raghunath Jadhav
Rukmini Smruti CO OP Society LTD
possession by Jun 2027 · Global Enterprises
Rumah Bali Phase 3
possession by Dec 2031 · Puranik Builders Limited
Rumah Bali Phase 4
possession by Dec 2028 · Puranik Builders Limited
Rumah Bali Phase 5
possession by Dec 2035 · Puranik Rumah Bali Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026