Mumbai/Project record

MahaRERA · the public record

Rumah Bali Phase 3

Bhainderpada · Puranik Builders Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

64units filed as unsoldInventory · 17 September 2026
30 Dec 2031declared completionMahaRERA registration · read 12 Jul 2026
615registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700015955

Delivery and registration

When is the project declared for completion?

Rumah Bali Phase 3 is registered with MahaRERA as P51700015955 and the promoter has declared completion for 30 Dec 2031.

30 Dec 2031

declared completion

63months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700015955
Registered on10 Apr 2018
Promoter-declared completion30 Dec 2031
Current statusCertificate Signed
Against today63 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Rumah Bali Phase 3 record 41 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 41 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Puranik Builders Limited is the promoter of record on 40 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

40projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Rumah Bali Phase 3, 457 of 521 homes filed with MahaRERA are recorded as sold or booked (450 with registered agreements and 7 booked), about 88%, and 64 remain available.

88%sold

457 of 521 homes

₹292.42 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹206.96 Cr (about 71%) is recorded as collected and ₹85.46 Cr as receivable. The project registers 615 homes in total, while this sold/unsold inventory filing covers 521 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 457 registered agreements, the effective carpet rate is ₹11,615/sqft, with eight in ten falling between ₹10,296 and ₹13,304 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 9 reserved, 6 owner/investor-held and 79 not for sale.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 457 homes carry one, and 64 of the 615 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
2802429 sqftRs 11,484 a sq ft typical, over Rs 4,560 to Rs 15,17189 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Rumah Bali Phase 3, 50 of the 64 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 63 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+43 and 615 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building Type C1G+4361531 Dec 2030

Unit mix on the filing: 568 residential and 47 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

18 complaints are on the MahaRERA record for Rumah Bali Phase 3, with orders passed in 5 of them.

18complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000037507204/04/2023Vikas Liladhar Patil vs Puranik Builders Limitedpending / no order on file
CC00600000042940424/02/2024Rupesh Chintaman Ambavane vs PURANIK BUILDERS LIMITEDorder passed
CC1250085412/03/2025arwaz Alam vs Puranik Builders Limitedorder passed
CC1250115507/04/2025Saikiran Ravikishore Gorge vs Puranik Builders Limitedorder passed
CC1250273304/08/2025Manohar Kistaswami Addagatla vs Puranik Builders Limitedorder passed
CC1260069306/02/2026ARUN UDAY PADHI vs Puranik Builders Limitedorder passed
CC1260093320/02/2026Pramod Sahadev Bhole vs Puranik Builders Limitedpending / no order on file
CC1260126709/03/2026Vinod Rajeshwar Charpilwar vs Puranik Builders Limitedpending / no order on file
CC1260196203/04/2026Puranik Builders Limited vs MOHAMMAD AMJAD SHAIKHpending / no order on file
CC1260256202/05/2026Ruturaj Mulik vs Puranik Builders Limitedpending / no order on file
CC1260316227/05/2026Rose Ukkan vs Puranik Builders Limitedpending / no order on file
CC1260268909/05/2026MANISHA KUMAR VAIBHAV JAISWAR vs Puranik Builders Limitedpending / no order on file
CC1260311125/05/2026Sanjay Kumar vs Puranik Builders Limitedpending / no order on file
CC1260340503/06/2026Vaishnavi Sanjay Tekade vs Puranik Builders Limitedpending / no order on file
CC1260398827/06/2026pankaj vishwas patil vs Puranik Builders Limitedpending / no order on file
CC1260416803/07/2026Chetan Anil Chavan vs Puranik Builders Limitedpending / no order on file
CC1260423306/07/2026Jayant Ravindra Kharat vs Puranik Builders Limitedpending / no order on file
CC1260451618/07/2026Soniya Abhijeet Patu vs Puranik Builders Limitedpending / no order on file

Legal & Litigation

The promoter has declared 8 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division ThaneSCS 2272011For Evidence
Bombay High Court123412015For Admission
Civil Judge Senior Division ThaneRCS 1462011For Evidence
Civil Judge Senior Division ThaneSCS 4662016Dispose Off
Bombay High CourtWP 3122019For Hearing
Bombay High Court60952021For Admission
Civil Judge Senior Division ThaneRCS 3652020For Amendment
District Consumer Dispute Redressal Forum3062020For Filing Evidence Affidavit

Location, Land & Connectivity

Located at Bhainderpada, Ghodbunder Road, Thane, Thane, 400615. Per the filed land record, the plot is bounded to the north by Amenity Plot, to the south by Adjacent S No 98-3part, to the east by 60m wide GB Road and to the west by New S No 100-19. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park19 km
Andheri MIDC / SEEPZ19 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district34 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Puranik Builders Limited is the promoter on 20 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Puranik Builders Limited project & its RERA track record →

Other flagged projects by Puranik Builders Limited

Puranik Builders Limited
FlaggedThane
Puranik Builders Limited
FlaggedRaigarh
Puranik Builders Limited
FlaggedRaigarh
Puranik Builders Limited
FlaggedRaigarh
Puranik Builders Limited
Deregistered by MahaRERARaigarh
Puranik Builders Limited
Deregistered by MahaRERARaigarh

Other RERA-registered projects in Owale

ACE Aristo
possession by Oct 2026 · Gaurav Land Corporation
Metro Hive D-1
possession by Dec 2026 · Vihang Infrastructure PVT LTD
Vihang Plaza - A Commecial
possession by Dec 2026 · Vihang Enterprises
Vihang Woods
possession by Dec 2026 · Vihang Enterprises
Ace Enclave
possession by Dec 2026 · Ace Signature Homes LLP
Cascade Avenue Bellagio
possession by Dec 2026 · Aarsh Construction

Major developers building in Owale

Other RERA-registered projects in Thane

Rumah Bali Phase 4
possession by Dec 2028 · Puranik Builders Limited
Rumah Bali Phase 5
possession by Dec 2035 · Puranik Rumah Bali Private Limited
Rumah Bali Phase 6
possession by Jun 2036 · Puranik Rumah Bali Private Limited
Runwal Dreams
possession by Dec 2027 · Vijay Gurunath Patil
Runwal Edge
possession by Sep 2027 · Runwal Residency Private Limited
Runwal Eirene - Part I
declared completion Jun 2025 · Runwal Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026