MahaRERA Property Intelligence · Thane
P51700015965 · Shil · promoter New India Construction
| MahaRERA registration | P51700015965 |
| Registered on | 10 Apr 2018 |
| Promoter-declared completion | 30 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 5 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~44.1% of the estimated project cost incurred as of the last certificate (₹5.76 Cr spent against a ₹13.06 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. With only ~5 months to the declared date and ~44.1% of the cost incurred, ask the promoter how the balance gets built in the time left.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 62 homes filed with MahaRERA, 53 are sold/booked (34 with registered agreements + 19 booked) and 9 remain available (~85% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹15.22 Cr in agreement value so far. Of that, ₹7.93 Cr (~52%) is already collected, ₹7.29 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 53 registered agreements, the effective carpet rate is ₹6,090/sqft (typical range ₹5,581–₹10,374) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 12 | 1204 | 354 sqft (32.91 sqm) | ₹26.66 Lakh |
| Floor 16 | 1602 | 515 sqft (47.84 sqm) | ₹42.83 Lakh |
| Floor 17 | 1701 | 515 sqft (47.84 sqm) | ₹42.78 Lakh |
| Floor 17 | 1702 | 515 sqft (47.84 sqm) | ₹42.78 Lakh |
| Floor 18 | 1801 | 515 sqft (47.84 sqm) | ₹42.78 Lakh |
| Floor 18 | 1802 | 515 sqft (47.84 sqm) | ₹42.78 Lakh |
| Floor 3 | 304 | 354 sqft (32.91 sqm) | ₹29.31 Lakh |
| Floor 6 | 604 | 354 sqft (32.91 sqm) | ₹30.78 Lakh |
| Floor 7 | 702 | 515 sqft (47.84 sqm) | ₹44.13 Lakh |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29 and 62 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Nasam Darul Amaan Wing B | 1 | G+29 | 30 | - |
| Nasam Darul Amaan Wing A | 1 | G+29 | 32 | - |
Unit mix on the filing: 54 residential and 8 non-residential (shops/offices).
18 complaints are on the MahaRERA record for this project, with orders passed in 18. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000210075 | 18/02/2022 | Musa Rashid Mohammed Isa Khan vs New India construction | order passed |
| CC006000000375337 | 20/04/2023 | Mohammed Amin Ismail Hingora vs New India Construction | order passed |
| CC006000000375354 | 23/04/2023 | Vasim Azmatali Khan vs New India Construction | order passed |
| CC006000000385427 | 28/04/2023 | Naheed Sufiyan Khan vs New India Construction | order passed |
| CC006000000375406 | 04/05/2023 | Mohammad Akbar Mohammad Mohsin sayyad vs New India Construction | order passed |
| CC006000000396361 | 23/06/2023 | Naziya Faizan Kudalkar vs New India Construction | order passed |
| CC006000000396143 | 20/06/2023 | Abdullah Bismillah Qureshi vs New India Construction | order passed |
| CC006000000396435 | 01/11/2023 | Khizer Ashfaque Ismail vs New India Construction | order passed |
| CC006000000396212 | 20/06/2023 | Mohammed Azam Qureshi vs New India Construction | order passed |
| CC006000000396385 | 25/06/2023 | Kamil Abrar Ahmed vs New India Construction | order passed |
| CC006000000396383 | 27/06/2023 | Abrar Ahmed Shaikh vs New India Construction | order passed |
| CC006000000408147 | 18/11/2023 | Mohammed Umar Muhibullah vs New India Construction | order passed |
| CC006000000408474 | 16/12/2023 | Asiya Noorali Khan vs New India Construction | order passed |
| CC006000000396408 | 27/06/2023 | Seher Mohiuddin Khan vs New India Construction | order passed |
| CC006000000396368 | 23/06/2023 | Mohammed Ishak MIrza vs New India Construction | order passed |
| CC006000000375348 | 22/04/2023 | Sameer Yusuf Ansari vs New India Construction | order passed |
| CC006000000396216 | 20/06/2023 | Shaheen Banoo Mohammed Aqueel Shaikh vs New India Construction | order passed |
| CC006000000398048 | 03/11/2023 | Abbas Mehboob Khan vs New India Construction | order passed |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Jun 2024 | 30 Dec 2026 | Due to shortage of material and labor not able to complete project please grant us extension till 30/12/2026 |
Located at Shil, -, Andheri, Mumbai Suburban, 400612. Per the filed land record, the plot is bounded to the north by S No 155-156, to the south by S No 154, to the east by S No 182-183 and to the west by S No 152-1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 14 km |
| Andheri MIDC / SEEPZ | 18 km |
| Chhatrapati Shivaji Int'l Airport | 19 km |
| Bandra Kurla Complex (BKC) | 20 km |
| Lower Parel / Worli business district | 28 km |
| Nariman Point / Fort | 34 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Nasam Darul Amaan Wing A and B?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
See every NEW India Construction project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026