Naval Baug building No 1 and 2B

Masoli · Ahura Mazda Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000015716

Delivery and registration

When is the project declared for completion?

Naval Baug building No 1 and 2B is registered with MahaRERA as P99000015716 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000015716
Registered on19 Mar 2018
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Naval Baug building No 1 and 2B record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ahura Mazda Developers is the promoter of record on 10 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Naval Baug building No 1 and 2B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Building No 1A1G+431 Mar 2021
Building No 1B1G+431 Mar 2021
Building 2B1G+431 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Masoli, Main Road, Dahanu, Palghar, 401602. Per the filed land record, the plot is bounded to the north by Building No 3, to the south by Gut No 179, to the east by Building No 2A and to the west by Gut No 179. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~91 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ91 km
Powai / Hiranandani business park93 km
Chhatrapati Shivaji Int'l Airport95 km
Bandra Kurla Complex (BKC)98 km
Lower Parel / Worli business district106 km
Nariman Point / Fort114 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ashagad

Ratnamani Residency A
possession by Dec 2026 · Bhavi Reality LLP
SAI Garden Residency
Not filing quarterly progress reports · possession by Mar 2027 · Shahji Enterprises
Samruddhi Apartment
possession by Dec 2027 · Not Available
Shambhavi Apartments
possession by Dec 2028 · Jayesh Balvant Jani
Shambhavi ROW Houses Phase 2
possession by Dec 2028 · Jayesh Balvant Jani
Landmark
possession by Apr 2029 · Anmol Developers

Other RERA-registered projects in Palghar

Navkar City
declared completion Dec 2021 · Navkar Developers
Navkar City Phase I Part 14
possession by Dec 2028 · Navkar Developers
Navkar City Phase I Part 2
possession by Dec 2026 · Navkar Estate And Homes Pvt Ltd
Navkar City Phase-I-Part-4
possession by Dec 2026 · Navkar Estate & Home Pvt Lts
Navkar City Phase I Part 5
declared completion Jun 2026 · Navkar Estate AND Homes PVT LTD
Navkar City Phase I Part 6
possession by Jun 2028 · Navkar Estate AND Homes PVT LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026