Mumbai/Project record

MahaRERA · the public record

NAVKAR PALAZZO

BABHAI NAKA · Navkar Infra Projects

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002187

Delivery and registration

When is the project declared for completion?

NAVKAR PALAZZO is registered with MahaRERA as P51800002187 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002187
Registered on31 Jul 2017
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NAVKAR PALAZZO record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Navkar Infra Projects is the promoter of record on 91 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

91projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NAVKAR PALAZZO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+33.

BuildingWingsFloorsDeclared completion
NAVKAR PALAZZO1G+3330 Dec 2025

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for NAVKAR PALAZZO, with orders passed in 4 of them.

5complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017160726/11/2019John Fernandes vs Navkar Infra Projectsorder passed
CC00600000017168226/11/2019John Fernandes vs Navkar Infra Projectsorder passed
CC00600000029231327/08/2022Avilon Domnic D'souza vs Navkar Infra Projectorder passed
CC00600000039783513/10/2023Mr Veeraiah B Ponugupti vs M/s Vivek Constructionorder passed
CC1260169225/03/2026Allwyn Mathew Joseph vs Navkar Infra Projectspending / no order on file

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Consumer CourtCC/701/20152015For Filing Of Written Arguments
Dindoshi Court14062016For Compliance
High Court3571991For Directions

Location, Land & Connectivity

Located at BABHAI NAKA, L T ROAD , Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by CTS NO 602, to the south by CTS NO 613, to the east by CTS NO 603- 590 and to the west by CTS NO 532- 612. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park16 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Navkar Infra Projects is the promoter on 6 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Navkar Infra Projects

Navkar Infra Projects
FlaggedMumbai Suburban

Other RERA-registered projects in Borivali West

Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan
Shikhhar
possession by Sep 2026 · Mahavir Land Developer
Swastik
possession by Sep 2026 · Reliance Corporation
Signet
possession by Oct 2026 · DG Builders

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Navkar Shatrunjay
possession by Aug 2028 · M/S OM Navkar Creatos LLP
Navkettan Pushpaangan
possession by Mar 2028 · Priti Constructions Private Limited
Navlabh
declared completion Apr 2026 · Not Available
Navnath Jayas
possession by Dec 2027 · Navnath Infrastructures Private Limited
Navnath Nandikesh
possession by Dec 2027 · Navnath Infrastructures Private Limited
Navrang Atlantis
possession by Jan 2029 · Oxford Worldone Realty LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026