MahaRERA Property Intelligence · Mumbai Suburban

NAVRANG OASIS

P51800021423 · RAM MANDIR · promoter Oxford Realtors (India)

Certificate SignedDue 30 Apr 2025

Delivery & Registration

MahaRERA registrationP51800021423
Registered on28 Jun 2019
Promoter-declared completion30 Apr 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Oxford Realtors (India) is the promoter of record on 15 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 124 homes filed with MahaRERA, 102 are sold/booked and 22 remain available (~82% sold) — selling steadily. Buyers have committed ₹115.69 Cr in agreement value so far. Of that, ₹96.99 Cr (~84%) is already collected, ₹18.69 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 102 registered agreements, the effective carpet rate is ₹19,343/sqft (typical range ₹17,302–₹23,062) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 10B/1001474 sqft (44.04 sqm)₹84.03 Lakh
Floor 10B/1004474 sqft (44.04 sqm)₹84.03 Lakh
Floor 11B/1101474 sqft (44.04 sqm)₹84.03 Lakh
Floor 11B/1104474 sqft (44.04 sqm)₹84.03 Lakh
Floor 13A/1302474 sqft (44.04 sqm)₹80.38 Lakh
Floor 14A/1402474 sqft (44.04 sqm)₹80.38 Lakh
Floor 16B/1601474 sqft (44.04 sqm)₹80.38 Lakh
Floor 17B/1701474 sqft (44.04 sqm)₹80.38 Lakh
Floor 23B/2303528 sqft (49.05 sqm)₹93.61 Lakh
Floor 5A/502474 sqft (44.04 sqm)₹76.73 Lakh
Floor 5B/501474 sqft (44.04 sqm)₹84.03 Lakh
Floor 6A/602474 sqft (44.04 sqm)₹76.73 Lakh
Floor 6B/601474 sqft (44.04 sqm)₹84.03 Lakh
Floor 6B/604474 sqft (44.04 sqm)₹84.03 Lakh
Floor 7A/703474 sqft (44.04 sqm)₹76.73 Lakh
Floor 7A/704698 sqft (64.85 sqm)₹1.13 Cr
Floor 7B/701474 sqft (44.04 sqm)₹84.03 Lakh
Floor 7B/704474 sqft (44.04 sqm)₹84.03 Lakh
Floor 8A/802474 sqft (44.04 sqm)₹76.73 Lakh
Floor 8B/801474 sqft (44.04 sqm)₹84.03 Lakh
Floor 9B/901474 sqft (44.04 sqm)₹84.03 Lakh
Floor 9B/904474 sqft (44.04 sqm)₹84.03 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27 and 124 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
NAVRANG OASIS1G+27124-

Unit mix on the filing: 111 residential and 13 non-residential (shops/offices).

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000016145907/11/2019Sharad Vasudeo Koli and Vasudeo Punaji Koli vs Oxford Realtors India Pvt Ltdorder passed
CC00600000019221817/01/2020Savita Jagannath Worlikar vs Oxford Realtors ( India ) Pvt Ltdorder passed
CC00600000029287303/10/2022ZAKIR RAZZAK CHUNAWALA vs OXFORD REALTORS (INDIA) PVT LTDorder passed
CC00600000030348111/12/2022Sachin Jayant Mayekar vs Hiren & Parbhat Patelorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The High Court Of Judicature At Bombay27742021Disposed
The High Court Of Judicature At Bombay69532020Disposed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
01 Nov 202231 Oct 2023DUE TO DELAY IN COMMENCEMENT CERTIFICATE WE WOULD LIKE TO REQUEST AUTHORITY TO GRANT EXTENSION FOR FURTHER 12 MONTHS.
01 Nov 202230 Apr 2025Due to the project was initially launched by Old Developers in 2005. However, from 2005 to 2018, по substantial development activity took place. In the year 2018, society terminate

Location, Land & Connectivity

Located at RAM MANDIR, SV ROAD, Borivali, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by BUILDING NO 3 SIDDHARTH NAGAR, to the south by BUILDING NO 1 SIDDHARTH NAGAR, to the east by 40 M WIDE SV ROAD and to the west by SIDDHARTH NAGAR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Navratna
declared completion Mar 2026 · Om Navratna Enterprises LLP
Navratnamala
declared completion Oct 2023 · Elegant Constructions
Nayana Niwas
declared completion Mar 2018 · H.d.associates
Nazareth Niketan
declared completion Mar 2019 · Milan Interbuilt Private Limited
NCK House
possession by Dec 2028 · Blue Stone Properties Private Limited
ND Enclave
declared completion Dec 2019 · N & D Constructions LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.