Mumbai/Project record

MahaRERA · the public record

NEELAM CHS LTD

Mumbai Suburban · JAI SHREE KRISHNA BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006960

Delivery and registration

When is the project declared for completion?

NEELAM CHS LTD is registered with MahaRERA as P51800006960 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006960
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEELAM CHS LTD record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEELAM CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
NEELAM CHS LTD1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by NALLA, to the south by 13 MTRS ROAD, to the east by PLOT NO 114 and to the west by PLOT NO 116. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park4 km
Bandra Kurla Complex (BKC)5 km
Lower Parel / Worli business district14 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
possession by Dec 2026 · MDM Realty LLP
Platinum Grandeur
possession by Dec 2026 · Platinum Strategic Developers LLP
Vengurlekars Chaitra
possession by Dec 2026 · Vengurlekars Shreesai Builders And Devel

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Neelam Chsl
possession by Dec 2026 · OM SAI Developers & Promoters
Neeldhara CO-Operative Housing Society Limited
possession by Mar 2031 · Konark Structural Engineers Private Limi
Neelgagan CHS Ltd
declared completion Jun 2025 · Swastik Realty Pvt Ltd
Neelkanth Prakash
declared completion Mar 2026 · Integrated Residences LLP
Neelkanth Tirth CO. OP. Housing Soc. LTD
declared completion Oct 2023 · Maverick Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026