NEPTUNE

P51700022785 · KAUSA, MUMBRA · promoter Sahyadri Grih Nirman

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51700022785
Registered on23 Oct 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sahyadri Grih Nirman is the promoter of record on 42 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
A WING1G+931 Dec 2022
B WING1G+831 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KAUSA, MUMBRA, NEAR KALSEKAR COLLEGE, Thane, Thane, 400612. Per the filed land record, the plot is bounded to the north by HUSAIN KHATIB, to the south by CHAWL, to the east by AL MANTASHA and to the west by EVER CONSTRUCTION. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sahyadri Grih Nirman is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Sahyadri Grih Nirman

Sahyadri Grih Nirman
FlaggedThane
Sahyadri Grih Nirman
FlaggedThane
Sahyadri Grih Nirman
FlaggedThane

Other RERA-registered projects in Mumbra

Celosia Avenue
possession by Sep 2026 · Pratima Construction
Quality Annex
possession by Sep 2026 · Quality Annex
YES Central Galleria
possession by Oct 2026 · Noble Enterprises
YES Central Galleria 1
possession by Oct 2026 · YES Enterprises
Sagar Enclave
possession by Dec 2026 · Kanchan Builders & Developers
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP

Major developers building in Mumbra

Other RERA-registered projects in Thane

Neptune Swarajya 4B
possession by Dec 2027 · Neptune Developers Limited
Neptune Swarajya Sector 1 - 1A
declared completion Jun 2018 · Neptune Developers Limited
Neptune Swarajya Sector 1-A13
declared completion Jun 2018 · Neptune Developers Limited
Neptune Swarajya Sector 1- A14
declared completion Jun 2018 · Neptune Developers Limited
Neptune Swarajya Sector 1- A15
declared completion Jun 2018 · Neptune Developers Limited
Neptune Swarajya Sector 1- A16
declared completion Jun 2018 · Neptune Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026