Mumbai/Project record

MahaRERA · the public record

NEST LEAF

TEMBODE · NEST INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000011341

Delivery and registration

When is the project declared for completion?

NEST LEAF is registered with MahaRERA as P99000011341 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000011341
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEST LEAF record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Nest Infra is the promoter of record on 96 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

96projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEST LEAF in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A1G+4-
B1G+4-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for NEST LEAF, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000029227007/08/2022Abhijit Asit Ganguly vs NEST INFRAorder passed

Location, Land & Connectivity

Located at TEMBODE, OPP RICE MILL, Borivali, Mumbai Suburban, 401404. Per the filed land record, the plot is bounded to the north by H NO 1, to the south by 6 MT WIDE ROAD, to the east by S NO 4 and to the west by H NO 1 A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~64 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park67 km
Chhatrapati Shivaji Int'l Airport69 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nest Infra is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Netra Aarambh - Building No 6
possession by Dec 2026 · One Palace Infrastructure
NEW Home Paradise
declared completion Dec 2021 · NEW Home Infrastrcture
NEW Kamal Kunj
possession by Dec 2030 · Shrimunisuvrat Buildcon LLP
NEW Kasturi Sadan
possession by Dec 2030 · Shiv Shakti Enterprises
New Mandar Co-Operative Housing Society Ltd
possession by Jun 2030 · S. P. Developers
NEW Matruchhaya
possession by Dec 2029 · OM Balaji Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026