Mumbai/Project record

MahaRERA · the public record

Netarwala Compound

DHARAVI · Mukon Constructions Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012419

Delivery and registration

When is the project declared for completion?

Netarwala Compound is registered with MahaRERA as P51900012419 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012419
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Netarwala Compound record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Netarwala Compound in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Building one1G+7-
Building two1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DHARAVI, BHATIYA NAGAR DHARAVI ROAD, Ward ABCD, Mumbai City, 400021. Per the filed land record, the plot is bounded to the north by 3-317, to the south by CS 101, to the east by CS 316 part and to the west by 6-317. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort0 km
Lower Parel / Worli business district8 km
Bandra Kurla Complex (BKC)16 km
Chhatrapati Shivaji Int'l Airport19 km
Powai / Hiranandani business park23 km
Andheri MIDC / SEEPZ23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nariman Point

Composite Building NO2
possession by Jun 2027 · Neumec AND Sangam JV
Shahid Nagar
possession by Dec 2027 · Neumec AND Sangam JV
OM Gurukrupa SRA CHS Prop Phase 1
Past its declared completion date · declared completion Dec 2022 · Moss Realtors Pvt Ltd

Other RERA-registered projects in Mumbai City

NEW Cuffe Parade -Lodha Altia
declared completion Mar 2022 · Lodha Developers Limited
NEW Cuffe Parade - Lodha Enchante
declared completion Jun 2019 · Lodha Developers Limited
New Cuffe Parade - Lodha Gardenia
declared completion Mar 2023 · Lodha Developers Limited
New National Market Annexe
possession by Dec 2027 · Suleman Haroon & Company
Nexsa Capital
possession by Jun 2027 · Nexsa A Realtors AND Developers Limited
Nexsa Sky Vista
possession by Jun 2027 · Nexsa A Realtors And Developers Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026