MahaRERA · the public record

COMPOSITE BUILDING NO2

NARIMAN POINT · NEUMEC AND SANGAM JV

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900018301

Delivery and registration

When is the project declared for completion?

COMPOSITE BUILDING NO2 is registered with MahaRERA as P51900018301 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

9months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900018301
Registered on22 Oct 2018
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today9 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for COMPOSITE BUILDING NO2 record 32 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Neumec And Sangam is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for COMPOSITE BUILDING NO2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
COMPOSITE BUILDING NO 21G+20-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas
30 Jun 202330 Jun 2025In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r
30 Jun 202530 Jun 2027We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues

Location, Land & Connectivity

Located at NARIMAN POINT, 207 REGENT CHAMBER, Mumbai City, Mumbai City, 400021. Per the filed land record, the plot is bounded to the north by 374, to the south by 366, to the east by 355PT and to the west by 373. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort0 km
Lower Parel / Worli business district8 km
Bandra Kurla Complex (BKC)17 km
Chhatrapati Shivaji Int'l Airport19 km
Powai / Hiranandani business park23 km
Andheri MIDC / SEEPZ23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Neumec AND Sangam JV is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Neumec AND Sangam JV

Neumec AND Sangam JV
FlaggedMumbai City

Other RERA-registered projects in Nariman Point

Shahid Nagar
possession by Dec 2027 · Neumec AND Sangam JV
OM Gurukrupa SRA CHS Prop Phase 1
Past its declared completion date · declared completion Dec 2022 · Moss Realtors Pvt Ltd
Netarwala Compound
Past its declared completion date · declared completion Dec 2021 · Mukon Constructions Pvt. Ltd.

Other RERA-registered projects in Mumbai City

Continental Horizon
possession by Dec 2030 · SMB INC
Corner OF Five
declared completion Mar 2026 · Ramniklal Dhanji Chhadva
Cornerstone Apex
declared completion Dec 2023 · Shree SAI Parshwa Developers LLP
Cosmos Platinum Business Park
declared completion Dec 2021 · J R Properties
Cote DE Orient
declared completion Dec 2021 · Vijay Dwellers Private Limited
CRD Aura
possession by Dec 2027 · CRD Blue Ocean LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026