Mumbai/Project record

MahaRERA · the public record

COTE DE ORIENT

Mumbai City · VIJAY DWELLERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900006635

Delivery and registration

When is the project declared for completion?

COTE DE ORIENT is registered with MahaRERA as P51900006635 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900006635
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for COTE DE ORIENT record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vijay Dwellers is the promoter of record on 86 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

86projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for COTE DE ORIENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
RAGHDEV BHUVAN1G+6-
COTE DE ORIENT1G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2020PENDING FOR OCCUPANCY CERTIFICATE AND MISC INTERNAL WORK
31 Dec 202031 Dec 2020PROJECT IS COMPLETED, OCCUPATION CERTIFICATE IS AWAITED
31 Dec 202030 Jun 2021DELAY DUE TO COVID 19 PANDEMIC SITUATION

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400019. Per the filed land record, the plot is bounded to the north by BY 26 FT ROAD, to the south by BY PLOT NO 478, to the east by BY PLOT NO 473-475 and to the west by BY 60FT ROAD HORMASJI ADENWALA ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ12 km
Nariman Point / Fort12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Matunga

Balkrishna Hills
possession by Sep 2026 · Oriental Contractors Private Limited
Gulraj Paradise
possession by Sep 2026 · M/S Reliable Construction
Signare
Past its declared completion date · possession by Sep 2026 · Tejukaya Buildcon
Chhaya
possession by Dec 2026 · Fortune Realty
Jade Acharya
possession by Dec 2026 · Raghavendra Acharya & Others
Shayona
possession by Dec 2026 · Devesh Narendra Jani

Major developers building in Matunga

Other RERA-registered projects in Mumbai City

CRD Aura
possession by Dec 2027 · CRD Blue Ocean LLP
Crescent Aria
declared completion Mar 2019 · Crescent Property Developers
Crescent Bay - T2
declared completion Mar 2019 · L&t Parel Project LLP
Crescent Bay - T3
declared completion Mar 2024 · L&t Parel Project LLP
Crystal VUE
possession by Dec 2027 · Vaedhaman Developers
Cynthiandra
possession by Dec 2026 · Shubh Laxmi Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026