Mumbai/Project record

MahaRERA · the public record

Signare

MATUNGA · Tejukaya Buildcon

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

4units filed as unsoldInventory · 12 September 2026
30 Sep 2026declared completionMahaRERA registration · read 12 Jul 2026
15registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900003280

Delivery and registration

When is the project declared for completion?

Signare is registered with MahaRERA as P51900003280 and the promoter has declared completion for 30 Sep 2026.

30 Sep 2026

declared completion

0months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900003280
Registered on05 Aug 2017
Promoter-declared completion30 Sep 2026
Current statusCertificate Signed
Against today0 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Signare record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 35 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Tejukaya Buildcon is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Signare, ₹16.01 Cr of a declared ₹20.06 Cr estimated project cost is reported as incurred, about 79.8%, as at the last certified filing with MahaRERA.

79.8%

₹16.01 Cr

of ₹20.06 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Signare, 10 of 14 homes filed with MahaRERA are recorded as sold or booked, about 71%, and 4 remain available.

71%sold

10 of 14 homes

₹27.86 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹26.36 Cr (about 95%) is recorded as collected and ₹1.50 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 10 registered agreements, the effective carpet rate is ₹30,552/sqft, with eight in ten falling between ₹28,641 and ₹40,778 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 161601806 sqft (74.89 sqm)₹2.05 Cr
Floor 171602806 sqft (74.89 sqm)₹2.05 Cr
Floor 181801313 sqft (29.1 sqm)₹79.70 Lakh
Floor 1818021,296 sqft (120.41 sqm)₹3.30 Cr

The inventory filing also declares: 1 owner/investor-held.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 10 homes carry one, and 4 of the 15 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1602806 sqftRs 2.5000 cr to Rs 2.9912 cr2 filed on this stack, floors 11–12

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In Signare, 2 of the 4 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 3 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24 and 15 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Signare1G+2415-

Unit mix on the filing: 15 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2026The project is fully completed, and we have obtained the Full Occupancy Certificate, as we need to apply for Project Closure, we are advised to take and extension and hence to clos

Location, Land & Connectivity

Located at MATUNGA , DR BABASAHEB AMBEDKAR ROAD, Mumbai City, Mumbai City, 400019. Per the filed land record, the plot is bounded to the north by Shanti Niketan Building, to the south by Ravi Kiran Building, to the east by Dr Babasaheb Ambedkar Road and to the west by Uttam Villa Building. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport7 km
Nariman Point / Fort11 km
Powai / Hiranandani business park12 km
Andheri MIDC / SEEPZ12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Matunga

Balkrishna Hills
possession by Sep 2026 · Oriental Contractors Private Limited
Gulraj Paradise
possession by Sep 2026 · M/S Reliable Construction
Chhaya
possession by Dec 2026 · Fortune Realty
Jade Acharya
possession by Dec 2026 · Raghavendra Acharya & Others
Shayona
possession by Dec 2026 · Devesh Narendra Jani
Jade Solitaire
possession by Mar 2027 · National Happy Homes

Major developers building in Matunga

Other RERA-registered projects in Mumbai City

Signature
possession by Dec 2026 · Prabhat Sadan Properties Private Limited
Sila Tower
possession by Dec 2031 · Sila Offices Private Limiited
Silver Heights
possession by Dec 2027 · Kshama Builders & Developers Private
Simana Building 2
possession by Sep 2031 · Bhoomi Properties
Simana - Wing A - Phase 1
declared completion Dec 2025 · Bhoomi Properties
Simana - Wing B - Phase 1
possession by Dec 2026 · Bhoomi Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026