Developer RERA record

Kumar Properties

Kumar Properties has 116 RERA-registered projects: 45 projects under construction, Bengaluru averaging 36% construction; 70 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

Mixed record
Delivery signal
45
Under construction
70
Past declared date
35%
Bengaluru inventory booked

Under construction

Under construction — 45 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
KUMAR PLUMERIABengaluru14%
47 East - APunepossession by Mar 2027
47 East - B Wing APunepossession by Jun 2027
47 East - B Wing B, C And DPunepossession by Dec 2028
47 East - C MhadaPunepossession by Apr 2027
Hillview Residency Building DPunepossession by Jun 2027
Hillview Residency Building EPunepossession by Jun 2027
Hillview Residency Building HPunepossession by Dec 2026
Hillview Residency Building IPunepossession by Dec 2026
Kumar Omkar ShreePunepossession by Dec 2027
Kumar Padmalaya B04 & B05Punepossession by Jun 2029
Kumar Palaash A2Punepossession by Oct 2028
Kumar Palladium PlazaPunepossession by Dec 2029
Kumar Palmcrest A6Punepossession by Mar 2029
Kumar PalmnestPunepossession by Dec 2030
Kumar PanachePunepossession by Dec 2027
Kumar Parc Residences - A1Punepossession by Nov 2026
Kumar Parc Residences - A2Punepossession by May 2028
Kumar Parc Residences - B1Punepossession by Oct 2030
Kumar Parc Residences - B2Punepossession by Dec 2027
Kumar Parth Tower C 2Punepossession by Mar 2028
Kumar Parth Tower C1Punepossession by Dec 2027
Kumar Parth Tower C3Punepossession by May 2030
Kumar Parv A, B, C, D AND EPunepossession by Dec 2031
Kumar Parv F, G AND HPunepossession by Dec 2028
Kumar Pebble Park JOY 1 - C1Punepossession by Dec 2026
Kumar Pebble Park JOY 2 - C2Punepossession by Dec 2026
Kumar Periwinkle-Wing B3Punepossession by Dec 2027
Kumar PrakrutiPunepossession by Oct 2026
Kumar Primeview E1Punepossession by Dec 2028
Kumar Primeview E2Punepossession by Dec 2028
Kumar Primeview E3Punepossession by Mar 2029
Kumar Primeview G2Punepossession by Dec 2030
Kumar Primeview G3Punepossession by Dec 2030
Kumar Prism Tower APunepossession by Dec 2031
Kumar Prospera - A7 And A8Punepossession by Jul 2027
Kumar Purab A3 BuildingPunepossession by Dec 2027
Kumar Sanctum - A2 And B2Punepossession by Dec 2026
MangroveMumbaipossession by Jan 2030
Palmspring Towers - A1, A2 And A3Punepossession by Dec 2028
Palmspring Towers - A4, A5 And B2Punepossession by Dec 2026
Palmspring Towers - A8, A12 And B1Punepossession by Nov 2029
Playtor Chakan Midc-Phase 1Punepossession by Jun 2027
Surbhi Sangeeta Co-Op. Housing Society LtdMumbaipossession by Dec 2026
THE PresidenceMumbaipossession by Sep 2028
Considering a specific Kumar Properties project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (70)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Kumar Kino PlatinumBengaluru2020-12
KUMAR PROSPERA (57.0% built)Bengaluru2025-06
AnvayaMumbai2024-11
Hill View Residency Phase I Project II Building A AND BPune2022-12
Hillvew Residency Phase I Project III Bldg N AND OPune2023-12
Hillview Residency P CommercialPune2025-09
Hillview Residency Phase IPune2019-05
KUL CourtMumbai2019-12
KUL CoutureMumbai2024-12
KUL EleganceMumbai2024-12
KUL TulipMumbai2020-12
Kul Utsav Ph 1 C BuildingPune2020-10
Kul Utsav Ph I E BuildingPune2020-11
Kul Utsav Phase I - Building DPune2020-10
KUL Utsav Phase I -Building FPune2019-12
KUL Utsav Phase I -Building GPune2023-06
Kumar MangalamPune2022-10
Kumar Palaash APune2024-06
Kumar Palaash A1Pune2025-07
Kumar Palaash BPune2024-06
Kumar Palmcrest A4 BuildingPune2023-08
Kumar Palmcrest A5Pune2025-12
Kumar Palmgrove A6Pune2024-04
Kumar Papillon A3 BuildingPune2025-01
Kumar Parc Residences - C MhadaPune2025-11
Kumar Pebble Park Anand 3- A1 Core3Pune2023-04
Kumar Pebble Park JOY 3 - C3Pune2026-02
Kumar Pebble Park Khushi 2- D2Pune2024-04
Kumar Pebble Park Khushi 3 - D3Pune2025-07
Kumar PiccadillyPune2025-05
Kumar Piccadilly Commercial BuildingPune2022-10
Kumar Piccadilly E BuildingPune2023-08
Kumar Piccadilly F BuildingPune2025-01
Kumar PrajwalPune2026-07
Kumar Pratham - A B C And ShopsPune2025-02
Kumar Pratham - D E GPune2025-06
Kumar Pratham - F MhadaPune2024-03
Kumar Pratik B BuildingPune2023-03
Kumar Primrose C BuildingPune2022-12
Kumar PrismPune2024-12
Kumar Prospera - A1 And A2Pune2023-02
Kumar Prospera - A3, A4 And A5Pune2024-04
Kumar Prospera - A6Pune2025-08
Kumar Samruddhi A6 And A7 BuildingPune2024-12
Kumar Sanctum - A1 And B1Pune2021-11
Kumar Selena A BuildingPune2024-12
Kumar VistaPune2018-11
Palmspring Bungalows - E1 To E6Pune2021-12
Palmspring Towers - A6, A7 And B3Pune2025-04
Park Infinia - B1 And B2Pune2025-10
Park Infinia - I1, I2, I3, J2, J3 And K1Pune2023-06
Park Infinia - L1, K3 And I4Pune2024-12
Park Infinia - L2, L3, L4, K4, K5 And J4Pune2024-09
Park Infinia Phase IIIPune2019-05
Park Infinia Phase IVPune2022-08
Pebble Park D1Pune2020-10
Peninsula - DPune2025-10
Peninsula CPune2024-10
Picasso - OPune2022-08
Picasso Phase IIPune2019-12
PiccadillyPune2018-12
Primus - APune2021-12
Princeville - A2, C2 And Conv Shop 2Pune2023-06
Princeville - B3 And C1Pune2019-05
Princeville - B4 And B5Pune2022-08
Priyadarshan - IPune2025-05
Priyadarshan - JPune2024-01
Selena BPune2019-03
Shantiniketan Phase II A3Pune2020-03
Shantiniketan Phase II A4Pune2020-03
Registered, no progress filed yet (1)click to expand
ProjectCity
KUMAR PLATINABengaluru

Figures are Kumar Properties's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.