Mumbai/Project record

MahaRERA · the public record

KUL ELEGANCE

Mumbai City · KUMAR URBAN DEVELOPMENT PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900006503

Delivery and registration

When is the project declared for completion?

KUL ELEGANCE is registered with MahaRERA as P51900006503 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900006503
Registered on14 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KUL ELEGANCE record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KUL ELEGANCE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
KUL ELEGANCE1G+8-

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for KUL ELEGANCE, with orders passed in 7 of them.

7complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000197217/11/2017PRAVIN CHAUDHARI vs KUMAR URBAN DEVELOPMENT LIMITEDorder passed
CC00600000000198918/11/2017DEB MAJUMDAR vs KUMAR URBAN DEVELOPMENT LIMITEDorder passed
CC00600000001214425/11/2017ANJANI KUMAR vs KUMAR URBAN DEVELOPMENT LIMITEDorder passed
CC00600000001253621/12/2017SUNIL KHANDELWAL vs KUMAR URBAN DEVELOPMENT LIMITEDorder passed
CC00600000002375616/03/2018OM PRAKASH KHANDELWAL vs KUMAR URBAN DEVELOPMENT LIMITEDorder passed
CC00600000005493220/06/2018JUHU ANAMIKA CO-OPERATIVE HSG SOCIETY LIMITED (society) vs KUMAR URBAN DEVELOPMENT LTD.order passed
CC00600000005652310/10/2018SUKETU OZA vs KUMAR URBAN DEVELOPMENT LIMITEDorder passed

A co-operative housing society is recorded as the complainant (JUHU ANAMIKA CO-OPERATIVE HSG SOCIETY LIMITED), and MahaRERA has passed an order.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Ld Sole Arbitrator D H Mehta2/20162015Final Order Passed On Eleventh November Two Thousand Nineteen
High CourtCABR/13/20162016Arbitrator Appointed
High Court664-20182018Suit Disposed Off As Per Consent Terms
High Court175-20162016Disposed

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400049. Per the filed land record, the plot is bounded to the north by BUILDING NO2-28T-S UNDER HIG, to the south by 18 WIDE ROAD, to the east by BUILDING NO 4 28T S UNDER HIG and to the west by GARDEN PLOT AND 59-93 SQMTRS MHADAS PLOT OF LAND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport4 km
Andheri MIDC / SEEPZ5 km
Bandra Kurla Complex (BKC)6 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Juhu

Elenora
possession by Sep 2026 · Parinee VIR Bhuvan Redevelopment Private
K L Valeria
possession by Sep 2026 · K L Housing LLP
Valletta
possession by Sep 2026 · K Raheja Corp Real Estate Private Limite
Maestro
possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Aditya Chsl
possession by Dec 2026 · Shree Mahavir Developers
Gurukrupa Alaknanda
possession by Dec 2026 · Gurukrupa Realcon Infrastructure Develop

Major developers building in Juhu

Other RERA-registered projects in Mumbai City

La Belleza
possession by Oct 2028 · Qaswa Enterprises
La Mer Residences
possession by Dec 2027 · Excellent Realtor Developers
La Verna
declared completion Dec 2019 · M/s Qaswa Enterprises
Labdhi Gardens Phase 2
declared completion May 2019 · Labdhi Lifestyle Limited
Labdhi Seabreeze
possession by Dec 2027 · Labdhi Siddhivinayak Realtors LLP
Lakadawala Garden
possession by Dec 2029 · M/s. Lakadawala Developers Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026