MahaRERA Property Intelligence · Mumbai City

CRYSTAL VUE

P51900006774 · Sion Koliwada · promoter Nageshwar Neela

Certificate SignedDue 30 Dec 2027

Delivery & Registration

MahaRERA registrationP51900006774
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nageshwar Neela is the promoter of record on 4 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~32.8% of the estimated project cost incurred as of the last certificate (₹29.51 Cr spent against a ₹89.85 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 45 homes filed with MahaRERA, 0 are sold/booked and 45 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+36 and 45 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Vue1G+3645-

Unit mix on the filing: 45 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court20892015Pending
Supreme Court71802015Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202730 Dec 2027The Developer was in process of commencing the development of the said project, however, due to the worldwide lockdown caused due to the COVID-19 pandemic, the Developer could not

Location, Land & Connectivity

Located at Sion Koliwada, J K Besan Marg, Ward FNorth, Mumbai City, 400037. Per the filed land record, the plot is bounded to the north by Om shiv Shakti CHS, to the south by Karmshetra Building, to the east by Dahmesh Gurudwara and to the west by Harbhansalal Marg. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Lower Parel / Worli business district5 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ12 km
Nariman Point / Fort12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wadala East

Brand One Wadala - A Wing
Not filing quarterly progress reports · possession by Aug 2026 · AM Constructions
Brand One Wadala - B Wing
Not filing quarterly progress reports · possession by Aug 2026 · AM Constructions
Nisarg CO Operative Housing Society Limited
possession by Dec 2026 · Cosmos Landmarks
Siddha Sky Phase 2
possession by Dec 2026 · M/s Sejal Shakti Realtors LLP
Siddha Sky Phase 3
possession by Dec 2026 · M/s. Sejal Shakti Realtors LLP
Building NO 6 Ajmera Greenfinity A Wing B Wing
possession by May 2027 · Ajmera Realty AND Infra India LTD

Major developers building in Wadala East

Other RERA-registered projects in Mumbai City

Cygnus
declared completion Jun 2022 · Trimity Developers Pvt Ltd
Cynthiandra
possession by Dec 2026 · Shubh Laxmi Developers
Dadamaharaj Heights
possession by Dec 2026 · Shree Vastudeep Developers
Daffodil
declared completion Dec 2021 · Buildarch Land Devlopers Pvt. Ltd.
Daffodil Heights
possession by Dec 2029 · Shree Krishna Constructions
Damodar Bhavan
declared completion Dec 2023 · Damodar Hirji & Baidevakavahu Charit

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026