Mumbai/Project record

MahaRERA · the public record

CORNERSTONE APEX

Mumbai City · SHREE SAI PARSHWA DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900013047

Delivery and registration

When is the project declared for completion?

CORNERSTONE APEX is registered with MahaRERA as P51900013047 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900013047
Registered on14 Sep 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CORNERSTONE APEX record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shree Sai Parshwa is the promoter of record on 33 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

33projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CORNERSTONE APEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
CORNERSTONE APEX1G+2031 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for CORNERSTONE APEX, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001268001/01/2018Pankaj Vora vs Shree sai parshwa developersorder passed

Location, Land & Connectivity

Located at Ward FNorth, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by PASSGE LEADING TO B S ROAD AND PLOT NO 537, to the south by INTERNAL ROAD AS MASJID GULLY, to the east by INTERNAL ROAD and to the west by INTERNAL ROAD AS MASJID GULLY AND PLOT NO 539. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar West

Arihant Tower
possession by Sep 2026 · Mehta Developers
Palette
possession by Sep 2026 · Suraj Estate Developers LTD
Vijayshree
possession by Sep 2026 · Sugee Eighteen Developers LLP
Yash Trinity
possession by Sep 2026 · Bhalchandra Vinayak Wadnerkar
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
possession by Dec 2026 · Nascent Developers

Major developers building in Dadar West

Other RERA-registered projects in Mumbai City

Cosmos Platinum Business Park
declared completion Dec 2021 · J R Properties
Cote DE Orient
declared completion Dec 2021 · Vijay Dwellers Private Limited
CRD Aura
possession by Dec 2027 · CRD Blue Ocean LLP
Crescent Aria
declared completion Mar 2019 · Crescent Property Developers
Crescent Bay - T2
declared completion Mar 2019 · L&t Parel Project LLP
Crescent Bay - T3
declared completion Mar 2024 · L&t Parel Project LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026