MahaRERA Property Intelligence · Mumbai Suburban

NORTHERN HEIGHTS

P51700007900 · DAHISAR EAST · promoter Rose Developers Pvt

Certificate SignedDue 30 Sep 2022

Delivery & Registration

MahaRERA registrationP51700007900
Registered on18 Aug 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rose Developers Pvt is the promoter of record on 15 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+53.

BuildingWingsFloorsDeclared completion
C WING1G+5331 Dec 2020
D WING1G+5331 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202231 Mar 2022DUE TO COVID 19 PANDEMIC AND SHORTAGE OF LABOUR THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 9 MONTHS

Location, Land & Connectivity

Located at DAHISAR EAST, S V ROAD, Borivali, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by NORTH, to the south by SOUTH, to the east by EAST and to the west by WEST. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park16 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

N.rose Developers PVT LTD is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by N.rose Developers PVT LTD

N.rose Developers PVT LTD
FlaggedMumbai Suburban
N.rose Developers PVT LTD
FlaggedThane

Other RERA-registered projects in Dahisar East

Sahakar Vista
possession by Jul 2026 · Sahakar Creation
Commercial Wing - NL Plaza And Residential Wing - NL Krishna
possession by Aug 2026 · Beautiful Properties Private Limited
Krishna Kripa
possession by Aug 2026 · Skyla Developers LLP
RAJ Capital
possession by Aug 2026 · RAJ Insignia Private Limited
Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

Notan Casa
declared completion Mar 2026 · Lifespace Homes Realtors LLP
Notan DC
possession by Sep 2029 · SSD Housing LLP
Notan Edge
possession by Dec 2028 · Notan Empress Private Limited
Notan House
possession by Mar 2027 · Notan House Private Limited
Notan Jewel
possession by Mar 2030 · SSD Properties LLP
Notan Tides
possession by Sep 2029 · Notan Residency Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026